PMP認證考試練習題及參考答案(三十三)
A total costs
B performance over a period of time
C costs at a point of time
D variable costs
E All of the above.
ans:C
2 Parametric cost estimating involves
A using the WBS to do bottom up estimates
B defining the perimeters of the life-cycle
C calculating the individual estimates of work packages
D using a statistical model to estimate costs
E A and C
ans:D
3 Which of the statements regarding benefit-cost analysis in the Special window are true?
A 1 and 2
B 2 and 3 www.Examda.CoM
C 1 and 3
D 1, 2 and 3
E None of the above.
ans:C
4 Present value measures
A the value to us today of future cash flows.
B the rate of return on an investment when we take account of cash inflows and outflows
C the current estimates of our project budget
D the dollars worth of work accomplished as of today
E All of the above.
ans:A
5 Using the situation stated in the Special window, what is the cost performance index for Case #9?
A 1.1
B 1.91
C 0.83
D 1.2
E None of the above
ans:A
6 Sunk costs are: 來源:www.examda.com
A future costs held in reserve.
B costs invested in commodities.
C expended costs over which we have no control.
D expended costs over which we have no more control
E tax credits
ans:D
7 Managerial Reserves are:
A allowances to account for price changes that can occur over the life of a project.
B incentive fees paid to managers for good performance.
C funds used to offset poor cost or schedule estimates.
D accounts to allocate and maintain funds for contingency programs
E All of the above.
ans:D
8 Life Cycle Costing:
A is the concept of including all costs within the total life of a project.
B is an activity devoted to optimizing cost/performance
C is an activity of appraising the cost and technical performance of a completed project.
D is a process of predicting the life of a project.
E None of the above.
ans:A
9 Using the situation stated in the Special window, what is the schedule variance for Case #8?
A 1000
B 2000
C -1000
D -2000 來源:考試大
E 0
ans:C
10 Using the situation stated in the Special window, what is the cost variance for Case #9?
A ¥-1,000
B ¥1,000
C -2000
D 2000
ans:E
B
11 Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?
A ¥3,605.00
B ¥0.57
C ¥567.00
D ¥892.86
E ¥3.61
ans:C
12 Using the situation stated in the Special window, what is net present value of an annual income flow of $1600 at 14% over the next three years?
A ¥3,713.60
B ¥0.68
C ¥1,080.00
D ¥476.19
E ¥2.32
ans:A
- 12015年咨詢工程師考試《宏觀經(jīng)濟》模擬題(4)
- 2廈門花20億打造中國首個"地下小鎮(zhèn)" 帶你體驗另類桃源
- 32013年二級建造師《施工管理》每日一練(11.5)
- 4聯(lián)合經(jīng)營的原則內(nèi)容
- 52015年云南省造價工程師考試報名時間為6月5日至7月5日
- 62015造價員復習資料:工程造價資料
- 7膨脹土地基變形量取值應符合規(guī)定
- 8景觀施工組織設計
- 9[山東]市政工程檢查井養(yǎng)護維修施工工法
- 10雙洞四車道分離式隧道施工組織設計(實施)
- 112015年咨詢工程師《工程咨詢概論》每日一練11.19
- 122015年咨詢工程師考試宏觀經(jīng)濟政策與發(fā)展規(guī)劃試題15
- 132015年咨詢工程師考試《項目決策分析與評價》模擬試題(八)
- 142015安全工程師押題試卷《生產(chǎn)技術》(5)
- 15武漢某體育中心防水施工方案
- 162015年造價工程師《理論與法規(guī)》知識點(18)
- 17工程施工測量技術中精度分析探討
- 182015年安全工程師考試《安全生產(chǎn)技術》資料:輸油氣站場
- 19某小區(qū)消防工程施工方案11P
- 20[四川省]06年安全工程師考試報名通知
- 21青海省2015年安全工程師考試網(wǎng)上報名資格審核人員聯(lián)系方式
- 222015年監(jiān)理工程師考試案例分析考前沖刺練(6)
- 23一級建造師管理與實務復習要點:柔性管道
- 24萬慶良落馬或與房地產(chǎn)腐敗有關 搭檔同學涉案
- 252015二級建造師《市政公用工程》城市道路工程(3)
- 26安全工程師答疑精華:一級發(fā)證
- 27一位考生借助網(wǎng)校通過監(jiān)理工程師考試后的心得
- 28工程施工過程中,為加快施工進度可采取的技術措施是
- 292015年天水造價工程師報名入口
- 30冰島阿庫雷里植物園“樹枝”咖啡館 獨特靈感造
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓