QUEST Using the situation stated in the Special window,   WBS Element Q is _____ budget by _____ percent. 
A Over, 16.66 
B Under, 16.66 
C Over, 10.0 
D Under, 10.0 
E None of the above. 
參考答案:A

QUEST Using the situation stated in the Special window,   the schedule performance index (SPI) for WBS Element P is: 
A 1.1 
B 0.9 
C 0.956 
D 1.15 
E 0.869 
參考答案:A

QUEST Using the situation stated in the Special window,   the cost performance index (CPI) for WBS Element R is: 
A 0.875 
B 1.14 
C 0.952 
D 0.833 
E 1.2 
參考答案:B

QUEST Using the situation stated in the Special window,  which WBS element has a favorable cost variance of $150? 
A Element P 
B Element Q 
C Element R 
D Element S 
E None of the above. 
參考答案:C

QUEST Using the situation stated in the Special window,  which WBS element is behind schedule but under budget? 
A Element P 
B Element Q 
C Element R 
D Element S 
E None of the above. 
參考答案:D

相關試題:

2010年PMP美國項目管理考試習題及答案五十二

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件