QUEST Cost forecasting calculations include: 
A EAC = ACWP + (BAC - BCWP) 
B EAC = BAC/CPI 
C EAC = ACWP + (BAC/CPI) 
D All of the above. 
E A and B 
參考答案:E

QUEST The Cost Performance Index (CPI) measures 
A total costs 
B performance over a period of time 
C costs at a point of time 
D variable costs 
E All of the above. 
參考答案:C

QUEST Parametric cost estimating involves 
A using the WBS to do bottom up estimates 
B defining the perimeters of the life-cycle 
C calculating the individual estimates of work packages 
D using a statistical model to estimate costs 
E A and C 
參考答案:D

QUEST Which of the statements regarding benefit-cost analysis in the Special window are true? 
A 1 and 2 
B 2 and 3 
C 1 and 3 
D 1, 2 and 3 
E None of the above. 
參考答案:C

QUEST Present value measures 
A the value to us today of future cash flows. 
B the rate of return on an investment when we take account of cash inflows and outflows 
C the current estimates of our project budget 
D the dollars worth of work accomplished as of today 
E All of the above. 
參考答案:A

相關(guān)試題:

2010年P(guān)MP美國項目管理考試習題及答案四十

試題推薦:

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件