QUEST Value engineering/Analysis is the systematic use of techniques which does not include _____. 
A establishing values for required functions 
B provide the required functions at the lowest overall cost. 
C identifies the required function of an item 
D seeks to trade performance for cost 
E None of the above. 
參考答案:D

QUEST The ability to achieve cost savings is inversely proportional to _____. 
A the earned value achieved to date 
B the estimated costs to complete 
C empowerment to the P.M. 
D productivity 
E None of the above. 
參考答案:A

QUEST The estimated cost to complete (ETC) is _____. 
A BCWP/ACWP 
B the forecasted and final cost - cost to date 
C (ACWP-BCWP)/BCWP * 100 
D Total estimate - ACWP 
E None of the above. 
參考答案:B

QUEST Considering alternate suppliers is a form of _____. 
A Value engineering. 
B Risk Analysis 
C Contract Management 
D Project integration 
E All of the above. 
參考答案:A

QUEST You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid.  The correct conclusion is: 
A The project is operating at a favorable cost efficiency ratio. 
B the project is spending more than planned 
C the project is behind schedule 
D the project is ahead of schedule 
E B and C 
參考答案:C

相關試題:

2010年PMP美國項目管理考試習題及答案三十九

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件