當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具
2012年pmp考試模擬試題及答案(四)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
QUEST Resource leveling _____.A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D
E
QUEST A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.
A Activity
B Event.
C Correlation
D Constant
E Event constrained within planned effort.
B
QUEST Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
A
QUEST The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF).
D Scheduled time (LF - ES).
E Event.
D
QUEST Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
A
QUEST Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A 0.5
B 1
C 1.8
D 2.2
E 2.8
C
QUEST In crashing a task, you would focus on:
A As many tasks as possible.
B Non critical tasks.
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
C
QUEST Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A 8
B 8.8
C 9.1
D 9.7
E 10.5
B
QUEST Using the WBS in the Special window, an instance of a work package is:
A Build house
B Excavate
C Prepare Foundation
D B and C
E None of the above
E
QUEST All of the following are categories of a milestone in a schedule except:
A End date.
B Contract dates.
C Key events scheduled.
D Imposed dates.
E Task duration.
E
QUEST The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
D
QUEST Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A Reduce.
B Eliminate.
C Double
D Increase
E Not affect
D
QUEST The key purpose of project control is to:
A Plan ahead for uncertainties.
B Generate status reports.
C Keep the project on track.
D Develop the project road map.
E All of the above.
C
QUEST Fast tracking means to:
A Speed up a project through parallel tasks.
B Swap one task for another.
C Reduce the number of tasks if possible.
D B and C.
E None of the above.
A
QUEST As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A Insignificant.
B Reduced.
C Unchanged.
D Increased.
E Doubled.
C
QUEST The purpose of a dummy activity in an activity-on-arrow diagram is to:
A Identify a task that could be replaced by another.
B Take the slack time into account.
C Show a task that is not necessarily needed.
D Denote a milestone.
E Show a dependency relationship.
E
相關(guān)推薦:2012年pmp考試模擬試題及答案(三)
- 12015年招標(biāo)師考試招標(biāo)采購案例分析復(fù)習(xí)指導(dǎo)(31)
- 209年注冊(cè)安全工程師事故案例分析模擬試題(三十九)
- 32015年安全工程師生產(chǎn)案例模擬練習(xí)(3)
- 4黑龍江人事考試網(wǎng)公布2015安全工程師報(bào)名時(shí)間:6月17日-6月30日
- 5黃土隧道施工方法
- 6肇慶市2015年注冊(cè)造價(jià)工程師報(bào)名時(shí)間為6月8日至7月2日
- 7采購成本分析預(yù)測(cè) 內(nèi)容
- 82015年招標(biāo)師考試《法律法規(guī)與政策》復(fù)習(xí)資料:第四章8
- 92013年二級(jí)建造師《法規(guī)及相關(guān)知識(shí)》每日一練(5.20)
- 10項(xiàng)目竣工驗(yàn)收的條件 主要內(nèi)容
- 11【招標(biāo)師考試】項(xiàng)目管理與招標(biāo)采購第三章:產(chǎn)品的項(xiàng)目設(shè)計(jì)管理
- 12某大橋上塔柱施工
- 132010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案一
- 142015年造價(jià)員基礎(chǔ)知識(shí):鋼筋計(jì)算其他問題
- 15一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):瀝青
- 16廈深鐵路潮州段率先完成鋪軌
- 17銀川:今年將新修200公里農(nóng)村公路
- 1808監(jiān)理工程師《案例分析》練習(xí)題8
- 19一級(jí)建造師《建設(shè)工程經(jīng)濟(jì)》考點(diǎn)解析(15)
- 202015年咨詢工程師考試《項(xiàng)目決策分析與評(píng)價(jià)》模擬試題(六)
- 21深基坑工程施工前應(yīng)取得的資料
- 22安全工程師《生產(chǎn)管理》考前自測(cè)題(8)
- 23世界第二座鋼板混合梁 懸索橋全線貫通
- 24四川安縣2012年投資審計(jì)節(jié)約1.72億建設(shè)資金
- 25海南2015年招標(biāo)師考試培訓(xùn)
- 262013年二級(jí)建造師《法規(guī)及相關(guān)知識(shí)》每日一練(11.5)
- 272015年咨詢工程師《宏觀經(jīng)濟(jì)政策與發(fā)展規(guī)劃》每日一練(2.28)
- 28園林景觀的施工組織設(shè)計(jì)
- 292015年安全工程師考試安全生產(chǎn)管理知識(shí)練習(xí)題(7)
- 302013年二級(jí)建造師《法規(guī)及相關(guān)知識(shí)》每日一練(11.22)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓