QUEST Project management provides organizations with a methodology to:
A Become more efficient and effective in accomplishing goals that cannot be handled well by
the traditional structure
B Manage high risk repetitive work
C Provide clients with multiple points of contact
D Provide guidance in accomplishing repetitive activities
E All of the above
A
QUEST Configuration (baseline) control monitors performance against the
A scope baseline
B original schedule
C original budget
D All of the above.
E None of the above.
A
QUEST A summary WBS is usually developed in the
A Conceptual phase
B implementation phase
C planning phase
D close-out phase
E All of the above phases
A
QUEST A project may be defined as _____
A an integrated approach to managing projects
B a coordinated undertaking of interrelated activities.
C a group of activities directed by a project manger over a life cycle
D an undertaking with a defined starting point and defined objectives
E All of the above.
D
QUEST Approval to proceed is normally made at the end of the _____ phase of a typical project.
A conceptual
B development
C implementation
D execution
E close-out
A
QUEST Lessons learned are most often based upon project historical records. Lessons learned can
be used to:
A See what mistakes others have made
B See how others have solved problems
C Predict trends, highlight problems and identify alternatives
D All of the above
E A and B only
D
QUEST A program can best be described as:
A A grouping of related activities which last two years or more
B The first major subdivision of a project
C A grouping of projects, similar in nature, which support a product or product line and
have no definable end point
D A product line
E Another name for a project
C
QUEST Ensuring that all work is both authorized and funded by contractual documentation is the
responsibility of:
A The project manager
B The functional manager
C The project sponsor
D The client
E All of the above
A
QUEST The project charter is a document designed to tell _____ exactly what the project
entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
E
QUEST Work authorization forms are needed in order to:
A Authorize line organizations to charge against the project
B Establish an audit trail
C Develop a structured methodology for release of funds
D All of the above
E A and C only
D
QUEST The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
E
QUEST Typical characteristics of a work package include:
A Representation of units of work at a level where work is performed
B Clearly distinguishes one work package from all others assigned to a single functional
group
C Limits the work to be performed to relatively short periods of time
D All of the above
E A and B only
E
QUEST Problems can occur in properly defining a project because:
A Project goals may not be agreeable to all parties
B The plan was "too loose," thus allowing priorities to change
C Low turnover of project personnel
D Too much communication between the client and project personnel
E The project objectives were quantified
A
QUEST In preparing a good project definition, experienced project managers will:
A Concentrate mainly on the end product rather than costs or benefits. These come later.
B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must
get beneath it.
C Understand that a project definition/plan is a dynamic rather than static tool, and thus
subject to change.
D Try to convert objectives into quantifiable terms.
E All of the above
E
QUEST Project life cycles provide a better means of measurement of progress and control. The
four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review
C
QUEST The contractual statement of work (CSOW)
A Must be the same as the proposal statement of work
B Does not identify reporting requirements
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D Identifies the contractor’s organizational structure for the project
E All of the above
C
QUEST Which of the following can result in misinterpretation of the statement of work?
A Using imprecise language (i.e. nearly, approximately)
B Mixing tasks, specifications, special instructions and approvals
C No pattern, structure or chronological order
D Wide variation in the size of tasks or details of work
E All of the above
E
QUEST A project manager believes that modifying the scope of the project may provide added value
for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project’s objectives
E Postpone the modification until a separate enhancement project is funded after this
project is completed according to the original baseline
E
QUEST The document authorizing functional areas to charge against the project is the:
A Work authorization form
B Scope baseline
C Project charter
D Management plan
E Linear responsibility chart
A
相關推薦:
2012年pmp考試模擬試題及答案(一)
- 1一級建造師管理與實務復習要點:補償收縮混凝土
- 2銅陵體育中心主體完工 “牡丹花”展現雄姿
- 3黑龍江:上半年全省農村泥草(危)房改造工作進展順利
- 4公園景觀工程施工組織設計63p
- 5地下管道接口金屬軟連接施工工法
- 6招標師職業(yè)水平考試:招標采購專業(yè)實務第八章練習題2
- 7PMP認證考試練習題及參考答案(四十)
- 8礦山水害及其防治技術
- 92013年二級建造師《法規(guī)及相關知識》每日一練(11.27)
- 10安全工程師生產法復習資料——安排試驗驗證項目
- 11黃山市2015年度注冊安全工程師考試報名時間為6月7日至13日
- 12高層住宅小區(qū)市政工程(雨污水、消防、給水)室外管網施工組織設計60P
- 132015年安全工程師考試《安全法及相關知識》習題6
- 14一級建造師公路工程管理與實務:鋼筋間隔綁扎
- 15社區(qū)地下防空洞數年內塌陷36次 領導多次視察仍無進展
- 162012一級建造師《機電工程》特種作業(yè)人員管理
- 17工程咨詢概論考點:項目后評價報告的基本格式
- 182015年咨詢工程師《工程咨詢概論》每日一練(9.9)
- 19[臺州市]06年安全工程師考試報名通知
- 202015年一級建造師《建設工程項目管理》知識摘要(1)
- 212015年咨詢工程師考試《宏觀經濟》模擬題(19)
- 22造價工程師復習資料:用銷售額和銷售單價表示的盈虧平衡點
- 23工程咨詢概論考試點:綜合評價法的概念
- 242015年招標師考試教材法律法規(guī)高頻考點:招投標活動法規(guī)
- 25溝通“信息孤島”創(chuàng)建ERP系統(tǒng)——關于開發(fā)建筑施工企業(yè)ERP系統(tǒng)的幾點思考
- 262015年咨詢工程師《工程咨詢概論》每日一練1.2
- 272015年咨詢工程師《工程項目組織與管理》每日一練12.25
- 282015年監(jiān)理工程師考試《工程合同管理》模擬題(7)
- 29朝鮮國際機場2號航站樓24小時施工 預定10月10日左右建成
- 30中鐵五局西成項目黃家梁隧道明洞成都方向貫通
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓