當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具
PMP認(rèn)證考試練習(xí)題及參考答案(五十五)
A Demand forecast
B Price forecast
C Supply forecast
D Production forecast
E None of the above.
ans:B
2 Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:
A Buyer
B Third party
C Contractor
D All of the above
E None of the above
ans:C
3 The _____ specification delineates specific measurable capabilities or parameters for which a product can be tested as part of the acceptance procedure.
A Performance
B Functional
C Technical 考試大-全國最大教育類網(wǎng)站(www.Examda。com)
D Base Line
E None of the above.
ans:A
4 There are four methods of government procurement. Which is not one of these methods?
A Assistance
B Sealed bidding
C Competitive proposals
D Acquisition
E Small purchases
ans:D
5 Which is not a consideration in a make or buy decision?
A Cost factors (least cost alternatives)
B Competitors' method of sourcing
C Existence of sufficient administration/technical personnel
D Political and social factors
E None of the above.
ans:B
6 By which means is a contractor able to control cost overruns due to changing requirements?
A Project data review
B Change order
C Purchase order amendment
D Change control
E None of the above.
ans:D
7 _____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form the basis of a contract.
A Request for proposal
B Invitation to bid
C Request for quotation
D Intention for bid
E None of the above.
ans:A
8 _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.
A Acquisition
B Contract negotiation
C Procurement
D Purchase negotiation
E None of the above.
ans:B
9 _____ is a narrative description of the work to be accomplished or resource to be supplied.
A Purchase order
B Level of effort work
C Scope of work
D Contract stipulation 考試大-全國最大教育類網(wǎng)站(www.Examda。com)
E None of the above.
ans:C
10 The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:
A Payment authorization
B Bid cost considerations
C Release payment
D Back charge
E None of the above.
ans:D
11 Cost Reimbursable contracts are equivalent to:
A Cost plus contracts
B Fixed plus contracts
C Progress payment contracts
D Back charge contracts
E None of the above.
ans:A
12 Which is not part of the purchasing cycle?
A Defined need
B Transmit need
C Inspection
D Prepare and issue purchase order
E A and D
ans:C
- 1一年花事完全手冊
- 2安全工程師考試《法律法規(guī)》習(xí)題班講義精選(176)
- 32012一級建造師《項(xiàng)目管理》:建設(shè)工程合同類型
- 4花崗巖鋪裝工程施工組織設(shè)計51p
- 5城市道路工程施工方案的技術(shù)經(jīng)濟(jì)分析
- 6磁懸浮軌道梁精密調(diào)位施工工法
- 7關(guān)于EPC模式與項(xiàng)目總承包模式承包范圍的說法,正確的是
- 8正確利用及保養(yǎng)攪拌車要領(lǐng)
- 9攪拌車保養(yǎng)的小竅門
- 10道路園林綠化、路燈、交通標(biāo)志施工方案135p
- 112013年二級建造師《施工管理》知識點(diǎn)整理:規(guī)費(fèi)
- 122015年果洛造價工程師考試用書
- 13二建復(fù)習(xí)資料砂漿配合的選擇
- 142013年二級建造師《施工管理》每日一練(11.7)
- 15經(jīng)濟(jì)合同變更、解除使一方受損失,如何賠償
- 16工程造價和審計咨詢兩行業(yè)轉(zhuǎn)型發(fā)展須抓兩手
- 17分包工程開工后施工情況進(jìn)行監(jiān)督檢查 內(nèi)容
- 18關(guān)于安全生產(chǎn)技術(shù)真題的一個問題
- 19附墻式外掛腳手架應(yīng)用與改進(jìn)措施
- 202015年咨詢工程師《項(xiàng)目決策分析與評價》每日一練8.6
- 212010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案31
- 222015年監(jiān)理工程師考試《工程合同管理》模擬題(3)
- 23一級建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):焊接連接
- 24北京:石景山兩重點(diǎn)村回遷房八成開建
- 252015年注冊安全工程師事故案例分析模擬試題(十九)
- 26招標(biāo)師職業(yè)水平考試:招標(biāo)采購專業(yè)實(shí)務(wù)第九章練習(xí)題9
- 27一級建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):簽發(fā)簽證問題
- 28提高產(chǎn)品價值的途徑
- 29《土建工程》知識點(diǎn):進(jìn)口設(shè)備的構(gòu)成
- 30給排水安裝基礎(chǔ)與識圖161P
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓