當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
PMP認證考試練習題及參考答案(二十四)
A time
B cost
C performance
D scope http://ks.examda.com
E None of the above.
ans:D
2 Which of the following are types of status reports?
A document, variance, trend and exception
B cost, trend, schedule and acquisition
C cost, schedule, technical performance
D analysis, cost, performance and schedule
E All of the above.
ans:C
3 You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked?
A Data item deliverables
B Customer-furnished equipment and facilities
C Long-lead procurement items
D Customer-imposed milestones
E Other subcontractor interface requirements
ans:A
4 During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to:
A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B Let the affected line groups decide among themselves who will perform the work
C Ask the executive sponsor to make the decision 來源:考試大網(wǎng)
D Allow each line group to perform part of the task
E All of the above
ans:B
5 The most common definition of project success is:
A Within time
B Within time and cost
C Within time, cost and technical performance requirements
D Within time, cost, performance and accepted by the customer/user
E None of the above
ans:D
6 The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
ans:E
7 The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project 考試大(www.Examda。com)
D Ill-defined requirements
E All of the above
ans:D
8 The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
ans:E
9 The "rolling wave" or "moving window" concept is used most frequently on projects where:
A The baseline is frozen for the duration of the project and no scope changes are permitted
B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes
C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
D Networking techniques are not appropriate
E All of the above
ans:C
10 Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager 來源:考試大
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
ans:C
11 Using the WBS shown in the Special window, a typical work package would be:
A Software development
B Systems design
C Coding
D A, B, and C
E None of the above.
ans:E
12 Feasibility studies evaluate alternatives in terms of
A Cost-effectiveness
B Ease of performance
C Risk
D Safety
E All or part of A through D
ans:E
- 12015年安全工程師考試《生產(chǎn)技術》模擬題匯總(1-9)
- 22015安全工程師《安全生產(chǎn)管理知識》每日一練(1.14-1.20)
- 32015年咨詢工程師考試練習題《工程咨詢概論》(5)
- 42015年安全工程師考試《安全生產(chǎn)法及相關》練習題(2)
- 5一級建造師管理與實務復習要點:線路列舉法
- 6招標師2015培訓機構(gòu)
- 72015造價員《土建工程》建筑鋼材:鋼筋
- 82015年造價工程師《理論與法規(guī)》專家講解(11)
- 9廈門市2008年度注冊安全工程師執(zhí)業(yè)資格考試5月15日至27日報名
- 10模板可調(diào)支座最大高度
- 11中建八局引領綠色建筑工業(yè)轉(zhuǎn)型 推進裝配式建筑
- 122015年監(jiān)理工程師考試理論與法規(guī)練習題(26)
- 132015年安全工程師考試《安全生產(chǎn)技術》練習題(6)
- 14工程咨詢概論知識點:工程咨詢方式及關注重點
- 15青島某帆船中心媒體中心地上部分施工組織設計大綱(魯班獎)
- 16某110KV變電所土建工程施工平面布置圖
- 172015年招標師《專業(yè)實務》:投標書的式樣和簽署
- 182015年注冊監(jiān)理工程師考試《合同管理》習題(1)
- 192015年招標師《專業(yè)實務》輔導:委托招標和自行招標
- 202010年PMP美國項目管理考試習題及答案27
- 21受煤坑、污水提升站施工方法
- 222008年安全工程師考試《安全生產(chǎn)技術》習題十一
- 2308監(jiān)理工程師《理論與法規(guī)》練習題9
- 242015造價工程師考試《計價與控制》教材精華(8)
- 252015招標師《項目管理與招標采購》:國內(nèi)貿(mào)易運輸方式
- 26工程施工中高支模技術的應用
- 27云南:麻昭高速公路建設啟動
- 28住宅小區(qū)工程施工進度計劃橫道圖(379工日)
- 2909年安全工程師事故案例分析模擬試題(四)
- 30大粒徑透水性瀝青混合料LSPM-25施工工法
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓