QUEST The review for the specification completeness is performed during which of the following cycles. 
A Award cycles 
B requirements cycle 
C requisition cycle 
D solicitation cycle 
E contractual cycle 
參考答案:C

QUEST In which of the following is the cost of risk hidden by the contractor? 
A Firm Fixed Price Contract 
B Fixed Price Plus Incentive 
C Cost Plus Fixed Price 
D Cost Plus Percentage of Cost 
E A and B 
參考答案:D

QUEST The definitive terms of a contract are written during which of the following contract phases? 
A Contract Phase 
B Post-Award Phase 
C Award Phase 
D Pre-Award Phase 
E Requirement Phase 
參考答案:C

QUEST The  _____   specification  delineates specific end use capabilities which can be tested in the acceptance procedure. 
A performance 
B functional 
C technical 
D base line 
E operational 
參考答案:B

QUEST Which one of the following is not an acquisition method? 
A advertising 
B invitation 
C negotiation 
D purchase 
E all are acquisition methods 
參考答案:A

相關試題:

2010年PMP美國項目管理考試習題及答案24

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:53    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件