2010年P(guān)MP美國項目管理考試習(xí)題及答案四十二

申請免費(fèi)試用、咨詢電話:400-8352-114

QUEST Using the situation stated in the Special window,  what is the cost performance index for Case #9? 
A 1.1 
B 1.91 
C 0.83 
D 1.2 
E None of the above 
參考答案:A

QUEST Sunk costs are: 
A future costs held in reserve. 
B costs invested in commodities. 
C expended costs over which we have no control. 
D expended costs over which we have no more control 
E tax credits 
參考答案:D

QUEST Managerial Reserves are: 
A allowances to account for price changes that can occur over the life of a project. 
B incentive fees paid to managers for good performance. 
C funds used to offset poor cost or schedule estimates. 
D accounts to allocate and maintain funds for contingency programs 
E All of the above. 
參考答案:D

QUEST Life Cycle Costing: 
A is the concept of including all costs within the total life of a project. 
B is an activity devoted to optimizing cost/performance 
C is an activity of appraising the cost and technical performance of a completed project. 
D is a process of predicting the life of a project. 
E None of the above. 
參考答案:A

QUEST Using the situation stated in the Special window,  what is the schedule variance for Case #8? 
A 1000 
B 2000 
C -1000 
D -2000 
E 0 
參考答案:C

相關(guān)試題:

2010年P(guān)MP美國項目管理考試習(xí)題及答案四十一

試題推薦:

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項目計劃軟件 項目進(jìn)度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件