2010年PMP美國項目管理考試習題及答案三十九

申請免費試用、咨詢電話:400-8352-114

QUEST The Cost Performance Index (CPI) measures: 
A cost of work performed vs planned costs. 
B work performed vs cost of work performed. 
C work performed vs planned work. 
D direct costs vs indirect costs. 
E floating costs vs. sunk costs. 
參考答案:B

QUEST Parametric estimates are based on variables such as: 
A Detailed planning and cost restraints. 
B Physical characteristics and historical data. 
C The WBS and similar projects. 
D Project objectives and manpower allocations. 
E Precise measurements and multiple inputs. 
參考答案:B

QUEST Cost and schedule data are usually integrated because: 
A optimized project cash flow can affect financial requirements 
B they provide MIS with an integrated system to produce reports 
C they control escalation allowances 
D they account for omissions in the definitive estimate 
E they predict future performance 
參考答案:E

QUEST Continually measuring and monitoring the actual cost versus the budget is done to _____. 
A analyze the reasons for variances 
B establish the variances 
C identify the problems 
D All of the above. 
E None of the above. 
參考答案:D

QUEST Using the cumulative cost curve in the special window, height B represents 
A actual cost to date 
B total budgeted costs for the project 
C planned cost for month 6 
D cost variance 
E earned value 
參考答案:B

相關試題:

2010年PMP美國項目管理考試習題及答案三十八

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件