QUEST A comparison of completion status to baseline is referred to as _____. 
A Earned value measurement. 
B Percent complete. 
C ACWP. 
D BCWS 
E None of above. 
參考答案:A

QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as: 
A Slack 
B Free float. 
C Restricted float. 
D Level float. 
E Lag 
參考答案:E

QUEST Overlapping activities on a project, such as design and construction, is referred to as: 
A Fast tracking 
B Risk conversion. 
C Parallel management. 
D Process improvement. 
E Synchronous manufacturing 
參考答案:A

QUEST A computer tape which contains historical project information is called ____ tape. 
A Database 
B Baseline. 
C Archive. 
D Lessons learned. 
E Life cycle summary. 
參考答案:C

QUEST Which method shown below is acceptable for reducing cost or shortening the schedule? 
A "Crashing" 
B Changing scope. 
C Performing activities in parallel rather than in series. 
D All of the above. 
E A and C only. 
參考答案:D

相關(guān)試題:

2010年P(guān)MP美國項目管理考試習(xí)題及答案三十三

試題推薦:

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件