2010年P(guān)MP美國項目管理考試習(xí)題及答案十五

申請免費(fèi)試用、咨詢電話:400-8352-114

QUEST Good project objectives must be: 
A General rather than specific 
B Established without considering resource bounds 
C Realistic and attainable 
D Overly complex 
E Measurable, intangible and verifiable 
參考答案:C

QUEST Researching, organizing and recording pertinent information is called: 
A Alternative analysis 
B Information gathering 
C Configuration management 
D Post project analysis 
E All of the above 
參考答案:B

QUEST The Work Breakdown Structure (WBS) is the basis for communicating: 
A Project scope, cost control, schedule, quality 
B Project objectives, dependencies, plan, cost control 
C Project scope, schedule, staffing, cost control 
D Project scope, quality, schedule, dependencies 
E Project budget, schedule, risk factors, work assignments. 
參考答案:A

QUEST The sequential steps that define the process for successfully completing a project is: 
A Implementation Plan 
B a life cycle 
C Development Plan 
D a critical path 
E Management Plan 
參考答案:B

QUEST What is the purpose of the Project Plan? 
A To document the Preliminary estimates. 
B To document the Definitive estimates. 
C To document the Budgetary estimates. 
D To document Parametric estimates. 
E To document Order of Magnitude estimates. 
參考答案:C

相關(guān)試題:

2010年P(guān)MP美國項目管理考試習(xí)題及答案十四

試題推薦:

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項目計劃軟件 項目進(jìn)度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件