當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
2010年PMP美國項目管理考試習題及答案三十
QUEST The first step in building a PERT/CPM network is to:
A Create a flow chart
B Determine the critical path
C Show task relationships
D Create a work breakdown structure
E None of the above.
參考答案:D
QUEST The critical path in a schedule network is the path that:
A Takes the longest time to complete
B Must be done before any other tasks
C Allows some flexibility in scheduling a start time.
D Is not affected by schedule slippage
E All of the above.
參考答案:A
QUEST Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:
A The project's schedule will be reduced by 2 weeks.
B The available slack on the noncritical paths will increase.
C A new critical path may appear after the crash.
D All of the above.
E A and B only.
參考答案:C
QUEST Your team has prepared a CPM schedule for your review. You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity). Select the correct statement from the following:
A This is a valid representation if the logic is correct.
B This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.
C This is invalid because nodes cannot have both dummy inputs and dummy outputs.
D This is a invalid because the number of outputs must equal the number of inputs.
E This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method.
參考答案:A
QUEST During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B Is still the original baseline but annotated to reflect that a change has taken place.
C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E Is the same since baseline schedules cannot change once the development phase is completed.
參考答案:C
相關試題:
2010年PMP美國項目管理考試習題及答案二十九
試題推薦:
2010年PMP美國項目管理認定考試全真模擬試題精選1
2010年PMP美國項目管理認定考試全真模擬試題精選2
2010年PMP美國項目管理認定考試全真模擬試題精選3
- 1酉沿高速重慶段首座長隧道貫通 全線有望2016年通車
- 2《現(xiàn)金咨詢方法與實務》知識點:設備及廠房系數(shù)法
- 3造價工程師復習資料:企業(yè)對項目經(jīng)理部可控責任成本的考核內容
- 42015安全工程師《生產(chǎn)管理知識》典型題(10)
- 5小心攪拌車發(fā)動機故障
- 62015年安全工程師考試《事故案例分析》模擬題(13)
- 7改性瀝青瓦施工工藝
- 813年福建造價員資格考試時間已作調整
- 9可不進行輕型動力觸探有哪些情況?
- 10PMP認證考試練習題(八)(中英文)
- 11重慶某隧道施工組織設計
- 122015年監(jiān)理工程師考試理論與法規(guī)練習題(54)
- 132015年監(jiān)理工程師《建設工程三大控制》練習題(125)
- 14CPMP、PMP及IPMP三種項目管理可比性的級別比較
- 152015年咨詢工程師《項目決策分析與評價》每日一練(6.17)
- 16廣東農村垃圾收運:戶收集、村集中、鎮(zhèn)轉運、縣處理
- 17關于安全生產(chǎn)法的“調整”
- 18±660kV換流站工程一級網(wǎng)絡計劃圖
- 192015年招標師考試考點:招標投標法律法規(guī)的主要規(guī)定
- 20瀝青混凝土路面機械攤鋪施工工法
- 21【達江解惑一】與名師對話 讓我們一起從平凡走向成功
- 222015年安全工程師考試《安全生產(chǎn)技術》:拆除工程
- 23北京管莊新樓外圍雨后下沉 施工人員稱不會影響
- 24湖南省益陽市2015年注冊安全工程師報名說明
- 252015年招標采購專業(yè)實務??季毩曨}七
- 262015年二級建造師《施工》:安裝工程費用的結算方法
- 27[中天]建筑工程實測實量操作手冊(結構、砌筑、抹灰)
- 282015年招標師法律法規(guī)政策考試練習題(23)
- 29象山市2015年安全工程師考試報名時間為4月14日至28日
- 30一級建造師實務復習要點:隱蔽工程
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓