1. Management decision-making includes:A. Analysis of alternatives.
B. Revisions/replanning.
C. Resource allocation.
D. Modification or updating of goals and objectives.
E. All of the above.
ANS: E
2. The basic terminology for networks includes:
A. Activities, events, manpower, skill levels and slack.
B. Activities, documentation, events, manpower and skill
levels.
C. Slack, activities, events, and time estimates.
D. Time estimates, slack, sponsorship involvement, and
activities.
E. Time estimates, slack time, report writing, life
cycle phases, and crashing times.
ANS: C
3. The project manager must receive reports and
briefings from engineers, contracting officers,
procurement personnel and marketing people.
The project manager’s communication dilemma is one of:
A. encoding
B. decoding
C. choice of a medium
D. one-way communication
E. All of the above.
ANS: E
4. The technique most commonly used to determine the
profitability of a project includes _____ methods.
A. Net present value (NPV).
B. Return on investment (ROI).
C. Discounted cash flow (DCF)
D. Payout time and risk sensitivity analysis.
E. All of the above.
ANS: E
5. Which of the following are part of the purchasing
cycle:
A. define need
B. prepare and issue purchase order
C. inspect incoming goods
D. All of the above.
E. A and B only
ANS: E
6. Which of the following is closest to Juran’s
definition of Quality:
A. conformance to requirements.
B. fitness for use.
C. continuous improvement.
D. customer focus.
E. All of the above.
ANS: B
7. A project element which lies between two events is
called:
A. An activity.
B. A critical path method.
C. A slack milestone.
D. A timing slot.
E. A calendar completion point.
ANS: A
8. Employee unions would most likely satisfy which
level in Maslow’s hierarchy of needs?
A. Belonging
B. Self-actualization
C. Esteem
D. Safety
E. Empowerment
ANS: A
9. Management calls a meeting to explain to all
employees the new benefits package for the rank and
file. This is an example of:
A. Upward communication
B. Downward communication
C. One-way communication
D. Two-way communication
E. None of the above.
ANS: C
10. Project management/project planning is most closely
aligned with:
A. Long range/strategic planning (5 years or more).
B. Intermediate range planning (1 to 5 years)
C. Short range/tactical planning (1 year or less).
D. All of the above.
E. B and C.
ANS: E
- 12015年安全工程師《安全生產(chǎn)法及法律知識(shí)》試題(7)
- 2工程技術(shù)交底的內(nèi)容
- 3[張家口]2008年度注冊(cè)安全工程師執(zhí)業(yè)資格考試5月7日至20日?qǐng)?bào)名
- 42015年度陜西省造價(jià)工程師報(bào)名時(shí)間為5月29日至6月21日
- 5城市廣場(chǎng)室外景觀綠化及排水工程施工組織設(shè)計(jì)40p
- 6河北省2015年安全工程師考試報(bào)名時(shí)間為4月22日至5月13日
- 7某工程采暖、給排水外線工程(結(jié)算資料)
- 8錘擊樁終止沉樁的控制標(biāo)準(zhǔn)應(yīng)符合哪些規(guī)定?
- 9【考后感言】高效備考二級(jí)建造師 一次性通過(guò)
- 10湖北:交投2013年將投資320億建高速公路232公里
- 112015年咨詢工程師《項(xiàng)目決策分析與評(píng)價(jià)》每日一練(12.17)
- 12安全工程師《安全生產(chǎn)技術(shù)》模擬題(二)
- 13淺談流線型建筑平面定位方法
- 14意外傷害保險(xiǎn)相關(guān)問(wèn)題
- 15柱的吊升方法有幾種
- 16南京市2015年造價(jià)工程師考試報(bào)名時(shí)間為6月1日-22日
- 17北京某高層酒店地下水防水施工方案(聚脂胎SBS改性瀝青防水卷材)
- 18北京公布2015年安全工程師考務(wù)文件
- 19一級(jí)建造師建筑工程復(fù)習(xí)要點(diǎn):制造成本
- 20項(xiàng)目經(jīng)理部人員調(diào)整
- 212015年二級(jí)建造師《施工管理》每日一練(7.12)
- 22什么是液壓式孔隙水壓力計(jì)?
- 23某公路瓦斯隧道實(shí)施性施工組織設(shè)計(jì)
- 242015年監(jiān)理工程師考試《建設(shè)工程三控》模擬練習(xí)(98)
- 25規(guī)劃的概念
- 26安全工程師《安全生產(chǎn)法及相關(guān)法律知識(shí)》模擬題(8)
- 27招標(biāo)師學(xué)習(xí)資料:確定中標(biāo)人的原則、步驟
- 28一級(jí)建造師建筑工程管理與實(shí)務(wù):鋼筋的綁扎
- 29一級(jí)建造師工程經(jīng)濟(jì)復(fù)習(xí)要點(diǎn):應(yīng)用方案經(jīng)濟(jì)分析順序
- 30內(nèi)蒙古首座大型抽水蓄能電站投產(chǎn)發(fā)電
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓