Qustions 1:As applied to projects, temporary means that--
a. Projects are short in duration
b. Every project has a definite beginning and end
c. The undertaking will end at an undetermined time in the future
d. Projects can be canceled at any time
Qustions 3:
Which of the following is an example a constraint in project plan development--
a. Records fo past performance
b. Financial reports from similar projects
c. A predefined budget
d. Lessons learned from prior projects
Qustions 5:
The management-by-objectives technique addresses all the following except--
a. Establishing unambiguous and realistic objectives
b. Periodically evaluating whether project objectives have been achieved
c. Promoting participation, team building, and commitment to the project
d. Establishing a specific career path for a project team member
Qustions 2:
All the following are examples of tools and techniques used in integration management except--
a. The work authorization system
b. Organizational procedures
c. Product skills and knowledge
d. Organizational policies
Qustions 4:
Performance measurement techniques are useful in overall change control because they --
a. Help show the status of the project
b. Measure overall project progress
c. Summarize information on the project for reporting to stakeholders
d. Help assess whether variances from the plan require corrective action
Qustions 6:
A work authorization system is a --
a. Work breakdown structure showing individual work elements
b. Formal procedure for sanctioning work so that it is done at the right time in the proper sequence
c. Method to ensure that each person on the project team knows the work elements that are his or her responsibility
d. System to help measure performance in terms of work completed versus work planned
- 1全國工程質(zhì)量存三問題 住建部將從本月起啟動(dòng)空前治理
- 22015年咨詢工程師每日一練免費(fèi)在線測(cè)試(2015.6.30)
- 3鉆孔灌注樁工藝框圖
- 4高層建筑基礎(chǔ)工程中預(yù)應(yīng)力管樁的施工技術(shù)
- 5衡茶吉鐵路炎陵縣境內(nèi)最后一座鐵路橋架設(shè)完畢
- 6監(jiān)理工程師復(fù)習(xí)過程中習(xí)題練習(xí)注意事項(xiàng)
- 72015年招標(biāo)師《專業(yè)實(shí)務(wù)》輔導(dǎo):采購的主要方式
- 8北京某科研設(shè)計(jì)業(yè)務(wù)樓工程地下室外墻及頂板防水施工方案
- 9園路工程課件
- 10某體育中心自來水改造工程施工組織設(shè)計(jì)
- 11建筑場(chǎng)地沉降觀測(cè)周期是多少?
- 12住宅主體結(jié)構(gòu)階段施工現(xiàn)場(chǎng)平面布置圖
- 13寧夏2015年度注冊(cè)安全工程師考試報(bào)名時(shí)間為5月1日至6月4日
- 142015造價(jià)員復(fù)習(xí)資料:什么是分部工程
- 152015年一級(jí)建造師建筑專業(yè)考點(diǎn):城市道路管理
- 162015年招標(biāo)師:招標(biāo)采購實(shí)務(wù)模擬試題11
- 17一級(jí)建造師項(xiàng)目管理復(fù)習(xí)要點(diǎn):索賠
- 182015年度南通市造價(jià)工程師報(bào)名時(shí)間初定為5月-6月
- 192015年造價(jià)工程師《計(jì)價(jià)與控制》教材精華(13)
- 202015年咨詢工程師《宏觀經(jīng)濟(jì)政策與發(fā)展規(guī)劃》每日一練(10.10)
- 212012年一級(jí)建造師《法規(guī)及相關(guān)知識(shí)》知識(shí)點(diǎn):國家保護(hù)的文物范圍
- 222015年咨詢工程師《現(xiàn)代咨詢方法與實(shí)務(wù)》試題(93)
- 23泰安市2015年安全工程師報(bào)名時(shí)間6月7日至6月21日
- 24監(jiān)理工程師考試2015《工程質(zhì)量與進(jìn)度控制》習(xí)題(3)
- 252013年二級(jí)建造師《法規(guī)及相關(guān)知識(shí)》每日一練(4.13)
- 26防水60問
- 272015年阿克蘇造價(jià)工程師準(zhǔn)考證打印時(shí)間
- 282015年安全工程師《安全生產(chǎn)管理知識(shí)》精華習(xí)題(48)
- 292015年監(jiān)理工程師應(yīng)試指南—《投資控制》內(nèi)容精選
- 30夏光:中國未來生態(tài)環(huán)境將面臨六大風(fēng)險(xiǎn)隱患
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓