PMP認(rèn)證考試試題精選(4)以及答案
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
61. At what point inthe project is there the most risk of project failure?A. Close out
B. Development
C. Implementation
D. Concept
62. Phase exits, kill points and stage gates are used for what purpose?
A. Planning the next stage in the project
B. Communicating milestones to stakeholders
C. Determining if the project should continue into the next phase
D. Measuring earned value
63. A complex project will fit best in what type of organization?
A. Functional
B. Cross-functional
C. Matrix
D. Balanced
64. Which knowledge area involves organizational theory as a tool/technique?
A. Communications Management
B. Cost Management
C. Risk Management
D. Human Resource Management
65. Human Resource Managenrnt is tightly linked to which other knowledge area?
A. Cost Management
B. Risk Management
C. Communications Management
D. Time Management
66. Which of the following is not considered a constraint in Organizational Planning?
A. Recruitment practices
B. Collective bargaining agreenrnts
C. Preferences of the project management team
D. Expected staff assignments
67. Outputs from Organizational Planning include all of the following except:
A. Staffing Management Plan
B. Organization Chart
C. Project Team Directory
D. Role and Responsibility Matrix
68. Inputs to Staff Acquisition include all of the following except:
A. Staffing Management Plan
B. Resource Histogram
C. Staffing pool description
D. Recruitment practices
69. Which of the following is not an input to Team Development?
A. Project Plan
B. Staffing Management Plan
C. Performance Reports
D. Reward and recognition systems
70. Cost Budgeting is defined as:
A. The estimated total cost of the project when done
B. Allocating the cost estimates to the individual work items
C. Estimating the cost of the resources needed to complete project activities
D. The sum of the approved cost estimates
71. The cost baseline is an output of what process?
A. Cost planning
B. Cost estimating
C. Cost budgeting
D. Cost control
72. The time phased budget that is used to measure and monitor cost performance is:
A. The project budget
B. The cost budget
C. The cost baseline
D. The cost estimate
- 12014年一級(jí)建造師《法規(guī)及相關(guān)知識(shí)》每日一練11.22
- 2某住宅小區(qū)項(xiàng)目地下室防水工程施工研究
- 32015年監(jiān)理工程師《理論與法規(guī)》每日一練(9.29)
- 4項(xiàng)目檢查
- 5建筑機(jī)械產(chǎn)能過(guò)多市場(chǎng)需求降低已是難題
- 6濟(jì)萊高速某隧道初期支護(hù)施工作業(yè)指導(dǎo)書
- 7勘察設(shè)計(jì)公司提升項(xiàng)目管理和會(huì)計(jì)核算質(zhì)量的辦法
- 8某廣場(chǎng)屋面找平層分項(xiàng)工程質(zhì)量技術(shù)交底
- 9電梯的制造、安裝、改造和維修的技術(shù)要求
- 10廣東省施工現(xiàn)場(chǎng)臨時(shí)用電安全施工組織設(shè)計(jì)編制要點(diǎn)
- 11從原材料角度預(yù)防混凝土收縮裂縫的產(chǎn)生
- 12高聳鋼結(jié)構(gòu)基礎(chǔ)頂面的錨栓有哪些設(shè)計(jì)規(guī)定?
- 13事故處理批復(fù)的法律屬性
- 14隧道防排水作業(yè)指導(dǎo)書
- 15中國(guó)五冶集團(tuán)華潤(rùn)雅安三九藥業(yè)工程開(kāi)工
- 16我國(guó)建筑業(yè)信息化該如何發(fā)展?
- 17安徽省住房城鄉(xiāng)建設(shè)系統(tǒng)法治工作座談會(huì)(南片)在合肥召開(kāi)
- 182015一建建設(shè)工程考試知識(shí)點(diǎn):工程成本核算的對(duì)象
- 19中國(guó)建筑一項(xiàng)技術(shù)破解隧道施工技術(shù)難題
- 202015造價(jià)工程師《計(jì)價(jià)控制》復(fù)習(xí)重點(diǎn)第八章(1)
- 21涂料原材料價(jià)格變動(dòng)是福是禍?
- 22深圳市某大廈工程安全技術(shù)交底
- 23用人單位違反作業(yè)場(chǎng)所防護(hù)管理的法律責(zé)任
- 24寧夏全國(guó)造價(jià)工程師資格考試輔導(dǎo)班/寧夏造價(jià)工程師資格考試培訓(xùn)班
- 256月3日:預(yù)計(jì)上海建材價(jià)格繼續(xù)弱穩(wěn)
- 26中鐵十四局長(zhǎng)株潭項(xiàng)目部舉行架橋機(jī)架設(shè)首孔雙線箱梁架設(shè)儀式
- 27一級(jí)建造師復(fù)習(xí)資料:道路壓實(shí)成型
- 28[黑龍江]76米長(zhǎng)預(yù)應(yīng)力鋼筋混凝土連續(xù)箱梁橋施工圖64張
- 29鋼框架結(jié)構(gòu)有哪些柱網(wǎng)布置?
- 30施工圖預(yù)算的編制依據(jù)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓