PMP美國項目管理認證模擬預測習題1

申請免費試用、咨詢電話:400-8352-114

1.These two processes in the Controlling process group are performedin parallel to assure correctness and acceptance of the work. Which are they?
A.Quality Assurance and Scope Verification
B.Quality Assurance and Scope Control
C.Quality Control and Scope Verification
D.Quality Control and Scope Control
1.在控制過程中有兩個過程同步進行以保證工作的正確性和驗收,這兩個過程分別是:
A.質量保證和范圍核實
B.質量保證和范圍控制
C.質量控制和范圍核實
D.質量控制和范圍控制
2.You are working on a project that is similar in scope to a projectperformed last year by your company.You might consider which of the following?
A.Using the previous project’s alternatives identification as atemplate
B.Reusing the previous project’s benefit/cost analysis asjustification for this project
C.Using the previous project’s WBS as a template
D.Reusing the previous project’s product description when writing thescope statement
2.你正在進行的一個項目和你公司去年進行的一個項目的范圍是類似的。你可以考慮下列哪一項?
A.利用從前項目的方案識別作為模板
B.重復利用從前項目的效益/成本分析作為驗證該項目的依據(jù)
C.利用從前項目的WBS作為模板
D.撰寫范圍說明書時重復利用從前項目的產(chǎn)品描述
3.You and a friend of yours have started your own consulting firm.Both of you are PMPs.You’ve given an estimate to aprospective client to manage a project they’re starting up next month.This is an important job, and thisclient would be an excellent reference for you if things go well.You know all of the followingstatements are true except:
A.Your estimate of costs should accurately reflect the services you’regoing to provide.
B.If you get the job, you should stick to the scope and objectives yououtlined in your bid or contract regarding the professional services you’llrender.
C.You should respect the confidentiality of the information you’llcome across during the course of this project.
D.Since it’s close to the holiday season, you send an expensive giftbasket to the client in the hopes they’ll pick your company to run this project.
3.你和你的一個朋友創(chuàng)立了一個咨詢公司,你們都是PMP。你接受了預期客戶于下月將要啟動的一個項目的估算。這個工作很重要,如果進展順利將會給你到來良好的資信證明。下面的說法中除了哪個以外都是正確的?
A.你的成本估算應當準確反映你將要提供的服務。
B.如果你得到這個工作,你應該按照你的標書貨合同中描述的范圍和目標提供你的專業(yè)服務。
C.你應當在項目期間遵守你可能遇到的保密信息的有關規(guī)定。
D.因為快要放假了,你給客戶送一個貴重的花籃以期客戶選擇你來管理項目。
4.The risk management plan accomplishes all of the following except:
A.It defines the methodology to risk management on the project.
B.It describes the risk categories.
C.It defines the roles and responsibilities of the risk managementteam.
D.It addresses responses to individual risks and how they will becarried out during the project.
4.風險管理計劃進行以下各項,但不包括:
A.定義項目風險管理的方法論
B.描述風險類別
C.定義風險管理團隊的角色職責
D.處理單個風險的應對以及在項目中如何實施
5.The expected value for your project duration estimate is 627 days,and the most likely duration estimate is 575. The standard deviation is 14. Which of the following statements is true?
A.A 95 percent confidence factor would make this project durationbetween 547 days and 603 days.
B.The project duration—given a 95 percent confidence factor—is between613 days and 641 days.
C.The project duration—given a 99 percent confidence factor—is between585 days and 669 days.
D.A 68 percent confidence factor would make this project durationbetween 547 days and 603 days.
5.項目歷時估算的預期值是627天,而最可能的歷時估算為575天,標準差為14天,
下面哪一種陳述是正確的?
A.按照95%的置信度,項目歷時定為547至603天
B.按照95%的置信度,項目歷時應為613至641天
C.按照99%的置信度,項目歷時應為585至669天
D.按照68%的置信度,項目歷時應為547至603天
6.If EV = 114, PV = 120, and AC = 103, what are CPI and SPI,respectively?
A.1.1 and 0.95
B.1.2 and 1.05
C.1.05 and 1.2
D.0.95 and 1.1
6.如果EV=114,PV=120,AC=103,那么CPI和SPI分別是多少?
A.1.1和0.95
B.1.2和1.05
C.1.05和1.2
D.0.95和1.1
7.You’re in the midst of managing a project for the water andsanitation district of your local city.It’s a large, complicated project that you’ve divided into smaller,manageable projects with their own project managers who all report to you. Two of these projects have beencontracted out to a vendor. You know that specific technical elements must be adhered to in thedesign and implementation of this project due to regulations governing thewater and sanitation district. Two other project managers in the district are busy working onunrelated projects, but they’re subject to the same regulations and processesas your project. Theseregulations won’t affect your next project, which you’ve learned is with thecity police department. Which of the following statements is not true?
A.The water and sanitation district prefers managing their projects ina coordinated fashion known as programs.
B.Phase exits are required for all vendor projects.
C.The projects in this district are considered an application area dueto their common elements.
D.Your project is employing the use of subprojects.
7.在你所在的城市,你管理一個水務局的項目,這是一個大型的復雜項目,所以你把它分解為更小的、可管理的項目,并任命了各自的項目經(jīng)理向你匯報,其中兩個項目外包給供應商。該項目必須達到相應的具體技術指標以滿足該局水務管理的有關規(guī)范。另外還有兩個項目經(jīng)理正在進行與該項目不相關的項目,但要符合和你的項目同樣的水務規(guī)范和流程。從市管理部門得知,這樣的規(guī)范不會影響到你未來的項目。下面那種說法是錯誤的?
A.該水務局愿意以協(xié)調的方式用大型項目來管理這些項目
B.所有外包項目需要階段把關
C.由于這些項目的共性,它們屬于一個專業(yè)領域
D.你的項目采用了子項目
8.If EV = 145, PV = 162, AC = 138, BAC = 200, what is EAC when youknow past estimating assumptions are no longer valid?
A.190.4
B.193
C.201
D.200
8.如果EV=145,PV=162,AC=138,BAC=200,如果你知道過去的估算假設已經(jīng)不復有效,那么EAC應該是多少?
A.190.4
B.193
C.201
D.200
9.All of the following statements are true regarding the TeamDevelopment process except for which one?
A.The output of Developing Project Team process is team performanceappraisals.
B.Team Development is performed during the Executing processes.
C.Team building activities include both management actions andindividual actions to improve team performance.
D.Collocation is a technique used to help the team perform better.
9.關于團隊發(fā)展,下面哪一個說法是錯誤的?
A.發(fā)展項目團隊的輸出是團隊績效評估
B.團隊發(fā)展是在執(zhí)行過程
C.團隊建設活動包括管理行為和個人行為以提高團隊績效
D.集中辦公是一種幫助團隊有更好績效的方法

相關試題:

PMP美國項目管理認證模擬預測習題2

PMP考試全真模擬題及答案(樣題)

PMP模擬習題匯總(附參考答案)

添加應用,免費套題體驗

發(fā)布:2007-03-02 10:46    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件