PMP認(rèn)證考試練習(xí)題及參考答案(三十)
申請(qǐng)免費(fèi)試用、咨詢(xún)電話(huà):400-8352-114
1 Using the figure in the Special window, The Critical path is _____ weeks.A 21
B 22
C 23
D 24
E 25
ans:D
2 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
A P
B Q
C R
D S
E T
ans:A
3 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A 0
B 1
C 2
D 3
E 4
ans:D
4 Using the figure in the Special window, The critical path is:
A A-B-G
B C-G
C C-D
D E-F
E A-B-G and C-D
ans:B
5 The first step in building a PERT/CPM network is to:
A Create a flow chart
B Determine the critical path
C Show task relationships
D Create a work breakdown structure
E None of the above.
ans:D
6 The critical path in a schedule network is the path that:
A Takes the longest time to complete
B Must be done before any other tasks
C Allows some flexibility in scheduling a start time.
D Is not affected by schedule slippage
E All of the above.
ans:A
7 Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:
A The project's schedule will be reduced by 2 weeks.
B The available slack on the noncritical paths will increase.
C A new critical path may appear after the crash.
D All of the above.
E A and B only.
ans:C
8 Your team has prepared a CPM schedule for your review. You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity). Select the correct statement from the following:
A This is a valid representation if the logic is correct.
B This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.
C This is invalid because nodes cannot have both dummy inputs and dummy outputs.
D This is a invalid because the number of outputs must equal the number of inputs.
E This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method.
ans:A
9 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B Is still the original baseline but annotated to reflect that a change has taken place.
C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E Is the same since baseline schedules cannot change once the development phase is completed.
ans:C
10 Network schedules are prepared during the _____ phase and updated during the _____ phase.
A Conceptual, execution.
B Development, implementation.
C Development, close-out.
D Implementation, close-out.
E Planning, finishing.
ans:B
11 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
A The project manager and project office personnel.
B The project team and functional managers.
C The project sponsor.
D All of the above.
E A and B only.
ans:E
12 Increasing resources on the critical path activities may not always shorten the length of the project because:
A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.
C The skill level of the added resources might not be appropriate for the activities to be performed.
D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)
E All of the above.
ans:E
- 1橡皮土怎么處理?
- 2全站儀后方交會(huì)在中小型礦井定向中的應(yīng)用探討
- 32015年咨詢(xún)工程師《工程項(xiàng)目組織與管理》每日一練(11.14)
- 42015年監(jiān)理工程師《三控》選擇第11-20題
- 5二級(jí)建造師法規(guī)知識(shí)點(diǎn):投標(biāo)文件的修改與撤回
- 6工業(yè)廠(chǎng)房工程施工進(jìn)度計(jì)劃?rùn)M道圖(自動(dòng)計(jì)算)
- 7四車(chē)道高速公路特長(zhǎng)隧道施工組織設(shè)計(jì)(133頁(yè))
- 8公路橋工程水泥混凝土方形灌注樁施工工法(中交)
- 9中糧成都鐵路專(zhuān)線(xiàn)竣工
- 10淺談煤礦井下火災(zāi)的搶救處理
- 11工程造價(jià)基礎(chǔ)知識(shí)建設(shè)工程招標(biāo):建設(shè)工程招標(biāo)的范圍
- 12某綜合樓水暖電安裝工程施工組織設(shè)計(jì) 39p
- 132015年招標(biāo)師考試招標(biāo)采購(gòu)專(zhuān)業(yè)實(shí)務(wù)考前復(fù)習(xí)指導(dǎo)(80)
- 142015年招標(biāo)師《專(zhuān)業(yè)實(shí)務(wù)》輔導(dǎo):招標(biāo)階段
- 152015年咨詢(xún)工程師考試練習(xí)題《工程咨詢(xún)概論》(7)
- 16框架剪力墻結(jié)構(gòu)適用范圍
- 17園林綠化景觀(guān)工程施工組織設(shè)計(jì)99p
- 18[內(nèi)蒙古]06年造價(jià)工程師考試6.8-11日網(wǎng)上補(bǔ)報(bào)名
- 192015年造價(jià)工程師考試輔導(dǎo):招標(biāo)投標(biāo)法
- 202015年二級(jí)建造師《法規(guī)》重點(diǎn):注冊(cè)建造師傅當(dāng)履行的義務(wù)
- 21市政公用工程施工項(xiàng)目目標(biāo)成本分析的內(nèi)容
- 22安全工程師《安全生產(chǎn)管理》第三講講義精選(12)
- 23名師達(dá)江解答二級(jí)建造師相關(guān)疑問(wèn)——報(bào)名篇(五)
- 24一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):標(biāo)書(shū)審查
- 25一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):路基的合格標(biāo)準(zhǔn)
- 262015年咨詢(xún)工程師《工程項(xiàng)目組織與管理》每日一練2.27
- 272012年pmp模擬試題及答案(八)
- 282015年福建造價(jià)工程師考試報(bào)名時(shí)間為6月28日-7月24日
- 29安全工程師《生產(chǎn)法及相關(guān)法律知識(shí)》預(yù)測(cè)試題(8)
- 30注冊(cè)咨詢(xún)工程師2015年《項(xiàng)目決策分析》習(xí)題(4)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓