1. overlapping activities on a project, such as design and construction, is referred to as:
a. fast tracking
b. risk conversion.
c. parallel management.
d. process improvement.
e. synchronous manufacturing來源:考試大網(wǎng)
ans: a
2. the major reason why a project manager would use written instead of oral communication is:
a. documentation
b. feedback
c. cost
d. barrier elimination
e. all of the above.
ans: a
3. the scope management provides:來源:考試大網(wǎng)
a. a basis for future decisions about the project.
b. a baseline to accomplish verification measures.
c. a baseline to evaluate potential scope changes.
d. all of the above.
e. b and c only.
ans: d
4. total project risk can be defined as:
a. the sum of the probabilities of project risks events times the sum of consequences of those risks
b. the sum of the products of each project risk event times its consequences
c. the sum of the consequences of all project risk events
d. the sum of the probabilities of all project risk events
e. 1 - the sum of the probabilities of all project risk events.
ans: b
5. which of the following statements about the cost of quality are true?
a. the cost of quality is the expense of nonconformance to requirements and specifications.
b. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.
c. quality control programs should be implemented when the cost of quality are deemed affordable by management.
d. a and b.來源:考試大
e. a and c
ans: a
6. a line manager who is asked to wear two hats and function as a project manager at the same time is likely to exercise:
a. authority
b. power
c. influence
d. all of the above]
e. a and b only
ans: d
7. including the customer in the process of project planning is:
a. slow and counterproductive.
b. essential in the definition and documentation of project goals.
c. necessary, but of limited value.
d. unnecessary because project goals are defined in the proposal stage.
e. none of the above.
ans: b
8. it is argumentative whether project managers actually control costs. which of the following is the most common element over which the
project manager may have some degree of control?
a. direct labor dollars
b. direct labor hours.www.Examda.CoM
c. overhead rates.
d. procurement costs.
e. none of the above.
ans: b
9. most quality problems:
a. originate in the quality department where the ultimate responsibility for quality rests.
b. originate on the shop floor because of waste and product rework.
c. are the results of management inattention to potential quality improvement ideas.
d. could be eliminated if shop supervisors monitored their work more closely.
e. a and b
ans: c
10. the "buy or make" decision is usually made during the:
a. acquisition cycle
b. contract evaluation cycle
c. requirements cycle
d. pre-award cycle
e. at any time that is convenient for the project manager
ans: c
11. the logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to
as:
a. slackwww.Examda.CoM
b. free float.
c. restricted float.
d. level float.
e. lag
ans: e
12. which of the following actions is an example of risk response:
a. adjust project parameters (scope, time, quality ...)
b. reduce the probability of potential project risk events
c. reduce the consequences of potential project risk events
d. wait until a problem actually happens, then deal with it in the most effective and efficient manner.
e. a, b and c only
ans: e
- 1廣州擬建廣州北站至白云機場快速通道分兩條
- 2青海:今年計劃完成公路建設投資52.8億元
- 3某110KV變電所(2)平面布置圖及說明
- 4某廣場景觀土建施工工藝
- 5高爐給料機危險分析
- 6EPS鋼絲網(wǎng)架板現(xiàn)澆混凝土外墻外保溫施工工藝
- 708年安全工程師《安全生產(chǎn)法及相關法律》習題二(無答案)
- 82015年造價工程師考試《理論與法規(guī)》課程講義(18)
- 92015年咨詢工程師《工程項目組織與管理》每日一練(11.17)
- 102015年安全工程師《安全生產(chǎn)法及相關法律知識》每日一練(3.8)
- 112015招標師考試科目《項目管理》:服務項目管理實施
- 12安全工程師生產(chǎn)法復習資料——甲級資質(zhì)條件
- 13安全生產(chǎn)事故案例分析:案例37及練習
- 142015安全工程師《生產(chǎn)管理知識》典型題(12)
- 152015年咨詢工程師《現(xiàn)代咨詢方法與實務》試題(63)
- 16[濰坊市]06年造價師考試6.15-30日報名
- 17自燃的發(fā)生及預防
- 182015咨詢工程師《項目決策分析與評價》模擬題(9)
- 19安全工程師考試《管理知識》練習精選(9)
- 20PMP認證考試練習題(四)(中英文)
- 212015年監(jiān)理工程師考試合同管理練習題(45)
- 22礪志PMP模擬題每周精選1
- 23[上海市]2005年度造價工程師續(xù)期注冊合格人員名單的通知
- 242015招標采購法律法規(guī)考點:中標通知書的性質(zhì)
- 25招標師考試的網(wǎng)絡課程學習
- 26碗扣式附墻電動升降鋼管升降后的安全要求
- 27自貢市2015年安全工程師考試報名時間確定:3月10日至4月10日
- 28沉降觀測中常遇問題及其分析與處理
- 29基礎梁的定義
- 30金壇新一輪村莊環(huán)境整治工作已全面拉開序幕
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓