當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案六
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
QUEST The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
參考答案:E
QUEST The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project
D Ill-defined requirements
E All of the above
參考答案:D
QUEST The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
參考答案:E
QUEST The "rolling wave" or "moving window" concept is used most frequently on projects where:
A The baseline is frozen for the duration of the project and no scope changes are permitted
B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes
C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
D Networking techniques are not appropriate
E All of the above
參考答案:C
QUEST Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
參考答案:C
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案一
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案二
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案三
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案四
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案五
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
- 1使用混凝土輸送泵應(yīng)注意十二點(diǎn)
- 2太中銀鐵路某隧道出進(jìn)口段施工組織設(shè)計(jì)
- 3二級(jí)建造師薪資
- 42015年陜西省安全工程師報(bào)名時(shí)間為4月8日-29日
- 52015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練8.21
- 62015年注冊(cè)監(jiān)理工程師《理論法規(guī)》習(xí)題(15)
- 72010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案28
- 82015二建備考中看過的知識(shí)點(diǎn)記不住怎么辦
- 9武漢CBD第64層建設(shè)如火如荼進(jìn)行中 預(yù)計(jì)明年春節(jié)前封頂
- 102015年咨詢工程師每日一練免費(fèi)在線測(cè)試(2015.6.8)
- 112015招標(biāo)師專業(yè)實(shí)務(wù)考點(diǎn):工程質(zhì)量的兩個(gè)控制環(huán)節(jié)
- 12二級(jí)建造師法規(guī)知識(shí)點(diǎn):建設(shè)工程合同
- 132015年安全工程師《生產(chǎn)管理知識(shí)》典型題(9)
- 14下列監(jiān)理工作措施中,屬于進(jìn)度控制技術(shù)措施的是
- 152015安全工程師《生產(chǎn)法及相關(guān)法規(guī)》提分試題(6)
- 16《工程咨詢概論》知識(shí)點(diǎn):工程咨詢業(yè)的特點(diǎn)
- 172015年安全工程師相關(guān)法律知識(shí)練習(xí)(9)
- 18某電視中心工程施工進(jìn)度總計(jì)劃
- 192015年安全工程師考試《事故案例分析》模擬題(9)
- 20什么是地震中的地聲現(xiàn)象
- 21受波浪沖擊駁岸植物生態(tài)護(hù)坡技術(shù)研究
- 222015年招標(biāo)師考試習(xí)題精選:資格預(yù)審文件的基本內(nèi)容
- 23內(nèi)蒙古某隧道出口施工組織設(shè)計(jì)
- 243年建造師考試坎坷路帶給您啟示
- 25我國(guó)將從六方面發(fā)展智能交通
- 262015年招標(biāo)師案例分析詳解(2)
- 272012年一級(jí)建造師《項(xiàng)目管理》:施工成本控制之三
- 28首鋼與中聯(lián)重科簽署戰(zhàn)略合作協(xié)議
- 29PMP如何填寫資格審核表
- 302015年造價(jià)員基礎(chǔ)知識(shí):電力電纜的分類
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓