PMP認證考試練習題(十九)(中英文)

申請免費試用、咨詢電話:400-8352-114

1. The highest attainable point in Maslow’s hierarchical diagram of needs is:
Basic, or physiological
Esteem
Team acceptance
Self actualization

在馬斯洛Maslow需要層次圖中,最高可達成點是:
a. 基本的或生理上的
b. 自尊
c. 團隊承認
d. 自我的實現

2. Which of the following personality attributes is not desired in a project manager?
Aversion to problem situations
Reliance on the team to resolve many of their own conflicts
Understanding of the project technology
Understanding of personnel problems

下列哪一項個人特質不期望在一個項目經理身上看到?
厭惡出現問題
依賴團隊來解決自己的很多沖突
理解項目技術
理解人事問題

3. Once Mike had completed the organizational planning for his project, he could successfully present which of the following to his sponsor?
Work breakdown structure, project plan, resource plan
Roles and responsibilities, risk plan, quality plan
Role and responsibility assignments, staffing management plan, project organization
chart
Project charter, project organization chart, roles and responsibilities, staffing plan

當麥克Mike完成了其項目的組織規(guī)劃, 他就能成功地向其業(yè)主呈現下列哪些事項?
工作分解結構, 項目計劃, 資源計劃
角色和責任,風險計劃, 質量計劃
角色和責任安排, 員工配置管理計劃, 項目組織圖
項目章程,項目組織圖,角色和責任, 員工配置計劃

4. Consider a project where core personnel from the functional areas are assigned to the project on a full-time basis, and the functional managers have no formal involvement. This situation describes an example of a:
Project matrix
Unbalance matrix
Non-functional organization
Project team

如果在一個項目中,來自職能領域的核心員工被安排專職做項目,但是職能經理并沒有正式參與. 這種情形描述著一個什么例子:
項目矩陣
非平衡矩陣
非職能性組織
項目團隊

5. You and your project team decide to use three time estimates per task to estimate durations. Your team is probably utilizing:
The PDM method
The PERT method
AWBS
CPM

你和你的項目團隊決定對每項工作使用三次估計來估算工時. 你的團隊可能在利用:
優(yōu)先圖示法PDM
計劃評審技術PERT法
實際工作分解結構AWBS
關鍵路線法CPM

6. Precedence Diagram Method (PDM) differs from Arrow Diagramming Method (ADM) primarily by allowing to represent .
Arrows, activity time durations
Nodes/boxes, events
Nodes/boxes, activities or work
Constraints, slack time

優(yōu)先圖示法 (PDM) 與箭線圖示法 (ADM) 的主要區(qū)別在于通過用 來表示 .
箭線, 活動持續(xù)時間
節(jié)點/方框, 事件
節(jié)點/方框,活動或工作
限制因素, 機動時間

7. The starting point in the development of a top-down CPM chart is the .
Project specification tree
Customer’s deliverable list
Customer’s milestone dates
Work Breakdown Structure

在制定自上而下的關鍵路線法CPM圖的起點是 .
項目規(guī)格樹
客戶的交付物目錄表
客戶的里程碑日期
工作分解結構

發(fā)布:2007-03-02 10:48    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]