PMP認(rèn)證考試練習(xí)題及參考答案(三十四)
A opportunity costs
B direct costs
C sunk cost
D unavoidable costs 來源:考試大網(wǎng)
E None of the above
ans:C
2 Which of the following types of cost are relevant to making financial decisions:
A sunk cost
B opportunity cost
C material cost
D A and C only 來源:考試大
E B and C only
ans:E
3 In which of the following cost estimating techniques are statistics models used:
A nonparametric cost estimating
B parametric cost estimating
C life cycle cost estimating
D bottom-up estimating
E All of the above.
ans:B
4 Under the terms of 2/10 net 30, the buyer may:
A deduct 10% of the invoice amount for payment within 30 days
B deduct 2% of the invoice for payment within 10 days
C incurs a penalty on 10% for payments more than 30 days late
D settle the invoice with 2 equal payments; one within 10 days and the other within 30 days
E None of the above
ans:B
5 Which of the following is referred to as payback period:
A the number of periods required to recover the initial investment
B the rate of return on the investment
C the number of periods required to bring project cost back to the original budget, based on current performance
D loan payment schedule
E None of the above
ans:A
6 Which of the following is referred to as sunk cost:
A management reserve
B contingency fund 來源:考試大
C cost budgeted for construction under water
D expended funds over which there is no further control
E forecasted budget over-runs
ans:D
7 The future value of an annual income flow of $1000 for 2 years at 10% is:
A ¥2,200
B ¥2,280
C ¥2,300
D ¥2,310
E None of the above
ans:D
8 The net present value of $110 one year from now at 10% is:
A ¥100
B ¥120
C ¥121 來源:www.examda.com
D $100 less taxes
E $100 less taxes and interest
ans:A
9 Which of the following depreciation methods provides for accelerated depreciation of an asset:
A Double declining balance.
B Straight line.
C Exponential depreciation
D Double sum of the years digits
E Double increasing balance
ans:A
10 Which of the following is considered a direct cost for producing a widget?
A The cost of the materials used to produce a widget.
B The labor costs of the workers who actually produced the widget.
C The rent for the building in which the widget was manufactured 來源:www.examda.com
D The salary of senior management and the project sponsor
E A and B only
ans:E
11 The reason that cost management is so difficult in project management is that:
A Projects by definition and nature are non-recurring events and are therefore difficult to predict.
B There are no tools for identifying project tasks.
C Project managers do not care about tracking costs, as only schedules are important to all project managers.
D A and B only
E B and C only
ans:A
12 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A Baseline costs
B Budgeted costs.
C Estimates upon completion costs
D Scheduled costs
E None of the above
ans:A
- 1寧夏7000萬元助推特色濱河新村建設(shè)
- 2污水處理廠施工方案65P
- 3聊城市2015年安全工程師考試報名時間為5月18日至6月4日
- 4混凝土泵的說明
- 5招標(biāo)師問答:服務(wù)招標(biāo)技術(shù)建議書
- 6壓縮純氧及其危險性分析
- 72015年造價工程師考試輔導(dǎo):施工單位計劃體系
- 82015年咨詢工程師每日一練免費在線測試(2015.1.12)
- 9北京某大型籃球館施工現(xiàn)場平面布置圖匯編(魯班獎)
- 10合(肥)福(州)客運專線閩贛段“四電”工程建成驗收
- 112015年造價工程師《理論與法規(guī)》講義精髓(15)
- 122015年和田造價工程師報名繳費時間及費用
- 13經(jīng)濟(jì)政策與法規(guī)考試點:產(chǎn)業(yè)調(diào)整主要原則
- 142015年安全工程師考試《安全生產(chǎn)技術(shù)》練習(xí)試題(9)
- 15地下工程結(jié)構(gòu)自防水的設(shè)計探討
- 16造價工程師案例分析復(fù)習(xí)要點:有關(guān)漲價預(yù)備費
- 17[湖北]2008年度注冊安全工程師執(zhí)業(yè)資格考試5月5日—14日報名
- 18山東省某汽車站TS防水卷材施工方案
- 19恩施州某醫(yī)院外科大樓工程防水施工方案
- 20全站儀在三角高程測量中的新應(yīng)用
- 21PMP美國項目管理認(rèn)證模擬預(yù)測習(xí)題1
- 222015招標(biāo)師成績:法規(guī)95,管理102,實務(wù)87,案例84
- 23國家電網(wǎng)公司工程造價與定額管理獲8項成果獎
- 24施工過程中發(fā)現(xiàn)文物而導(dǎo)致的停工該怎么索賠?
- 25招標(biāo)師職業(yè)水平考試:項目管理與招標(biāo)采購第一章練習(xí)題6
- 262015年注冊安全工程師事故案例分析模擬試題(八)
- 27某市政污水管道施工組織設(shè)計 10p
- 28吉林:今年擬建農(nóng)村公路3300公里 圓農(nóng)民致富夢
- 29甘肅省2015年造價工程師報名時間為6月18日至30日
- 302015年吐魯番造價工程師考試用書
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓