PMP認證考試練習題及參考答案(三十二)
A Reveals interdependencies.
B Facilitates "what if" exercises.
C Highlights critical activities.
D Provides information on resource requirements, time requirements and tradeoffs.
E All of the above.
ans:E
2 The major disadvantage of a bar chart is:
A Lack of time-phasing.
B Cannot be related to calendar dates.
C does not show activity interrelationships. 來源:考試大
D Cannot be related to manpower planning.
E Cannot be related to cost estimates.
ans:C
3 The most common types of schedules are Gantt charts, milestone charts, line of balance, and:
A Networks.
B Time phased events.
C Calendar integrated activities.
D A and C only.
E B and C only.
ans:A
4 Scheduling is the process by which decisions are made concerning:
A Tasks to be accomplished.
B Personnel/organization that will be assigned to accomplish the task.
C Time when the tasks are to be completed.
D All of the above.
E A and C only.
ans:E
5 Time management is the allocation of time in a project's life cycle through the process of:
A Planning
B Estimating.
C Scheduling.
D Controlling 考試大(www.Examda。com)
E All of the above.
ans:E
6 Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:
A $19K
B $21K
C $26K
D $29K
E indeterminate
ans:C
7 Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A Become worse, become worse
B Become worse, improved
C Improved, increased
D Improved, become worse
E None of the above are correct
ans:B
8 The computation for Cost Performance Index is:
A BCWP/ACWP
B BCWP-ACWP 來源:www.examda.com
C BCWP-BCWS
D ACWP/BCWP
E ACWP-BCWS
ans:A
9 When comparing the cost of competing projects, which of the following is typically NOT considered?
A Opportunity costs.
B Direct costs.
C Sunk costs.
D Indirect costs.
E Burden rates.
ans:C
10 The Cost Performance Index (CPI) measures:
A cost of work performed vs planned costs.
B work performed vs cost of work performed.
C work performed vs planned work.
D direct costs vs indirect costs.
E floating costs vs. sunk costs.
ans:B
11 Parametric estimates are based on variables such as:
A Detailed planning and cost restraints.
B Physical characteristics and historical data.
C The WBS and similar projects. 來源:www.examda.com
D Project objectives and manpower allocations.
E Precise measurements and multiple inputs.
ans:B
12 Cost and schedule data are usually integrated because:
A optimized project cash flow can affect financial requirements
B they provide MIS with an integrated system to produce reports
C they control escalation allowances
D they account for omissions in the definitive estimate
E they predict future performance
ans:E
- 12015一級建造師《法規(guī)及相關知識》沖刺指導(10)
- 2壓力容器焊接接頭設計
- 32015年造價工程師考試《理論與法規(guī)》課程講義(12)
- 4IPMP申請:IPMP認證費
- 5工程咨詢概論考點:投資的定義與分類
- 62015年武威造價工程師報名入口
- 7工程造價精華50條(一)
- 82015招標師考試項目管理考點:變更與洽商
- 92015招標師考試教材:合同的訂立與效力
- 10濱綏線牡丹江至綏芬河段擴能改造工程某隧道(實施)施工組織設計
- 11農(nóng)遷房工程給水管網(wǎng)安裝施工組織設計50p
- 12造價工程師建設工程計價復習資料——我國與世界銀行的合作
- 13一級建造師管理與實務復習要點:正反循環(huán)鉆孔
- 14攪拌車發(fā)動機常見的故障原因分析
- 152015年監(jiān)理工程師考試理論與法規(guī)練習題(58)
- 16名師達江解答二級建造師相關疑問——報名篇(六)
- 172012一級建造師《建筑工程》:地基基礎常見質量通病
- 182015年咨詢工程師《工程咨詢概論》每日一練4.7
- 19山東煙臺西港區(qū)億噸大港 欲建世界最大碼頭
- 202015年招標師考試《招標采購案例分析》模擬試題(4)
- 212015年招標師考試《法律法規(guī)與政策》復習資料:第一章9
- 22中鐵建工集團有限公司公開招聘公告
- 23某工程園林綠化施工組織設計
- 24咨詢工程師《宏觀經(jīng)濟政策與發(fā)展規(guī)劃》自測題(32)
- 252006年度全國監(jiān)理工程師資格考試建設工程監(jiān)理基本理論與相關法規(guī)試卷及答案
- 262015年一級建造師《工程經(jīng)濟》第三篇沖刺講義(5)
- 27某職工宿舍樓工程施工進度計劃網(wǎng)絡圖(CAD版)
- 28西安某工程完整周期建設方進度計劃
- 292015年一級建造師《公路工程》路面工程施工(2)
- 30世界貿(mào)易組織《政府采購協(xié)議》的主要內容
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓