當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
項目管理:PMP模擬題精選4
As applied to projects, temporary means that--
a. Projects are short in duration
b. Every project has a definite beginning and end
c. The undertaking will end at an undetermined time in the future
d. Projects can be canceled at any time
Qustions 3:
Which of the following is an example a constraint in project plan development--
a. Records fo past performance
b. Financial reports from similar projects
c. A predefined budget
d. Lessons learned from prior projects
Qustions 5:
The management-by-objectives technique addresses all the following except--
a. Establishing unambiguous and realistic objectives
b. Periodically evaluating whether project objectives have been achieved
c. Promoting participation, team building, and commitment to the project
d. Establishing a specific career path for a project team member
Qustions 2:
All the following are examples of tools and techniques used in integration management except--
a. The work authorization system
b. Organizational procedures
c. Product skills and knowledge
d. Organizational policies
Qustions 4:
Performance measurement techniques are useful in overall change control because they --
a. Help show the status of the project
b. Measure overall project progress
c. Summarize information on the project for reporting to stakeholders
d. Help assess whether variances from the plan require corrective action
Qustions 6:
A work authorization system is a --
a. Work breakdown structure showing individual work elements
b. Formal procedure for sanctioning work so that it is done at the right time in the proper sequence
c. Method to ensure that each person on the project team knows the work elements that are his or her responsibility
d. System to help measure performance in terms of work completed versus work planned
- 12015年咨詢工程師《項目決策分析與評價》每日一練(12.1)
- 2招標采購專業(yè)實務復習心得順口溜
- 3居住區(qū)種植設計總平面圖
- 42015年咨詢工程師《政策與規(guī)劃》每日一練(3.16)
- 5某工程深基坑防水噴錨網支護技術探討
- 6湖北某高速公路隧道施工組織設計
- 72015年監(jiān)理工程師《建設工程三大控制》練習題(54)
- 8工程造價基礎知識:工程財務
- 9深基坑支護施工中常見的問題
- 102015年安全工程師考試《事故案例分析》試題(11)
- 11增量來自產品創(chuàng)新,應用技術有待優(yōu)化——再談自粘卷材給防水施工帶來的巨大變革
- 12招標師復習資料:建設系統(tǒng)招標要求(2)
- 132015年咨詢工程師《宏觀經濟政策與發(fā)展規(guī)劃》每日一練(8.21)
- 14京滬高速鐵路某標段某隧道工程(實施)施工組織設計
- 152015年咨詢工程師每日一練免費在線測試(2015.1.4)
- 16打樁順序如何確定,順序安排不合理對工程質量有什么影響
- 172015年注冊咨詢工程師工程項目組織與管理習題(8)
- 18濰坊市2015年安全工程師考試報名時間擬定于5月20日至6月15日
- 19pmp項目管理:質量管理練習題1
- 20靜態(tài)GPS在工程測量中的應用體會
- 21一級建造師考試《機電工程》七大典型題型
- 222015年安全工程師考試《安全生產法》輔導資料(5)
- 23某高層大廈消防工程施工組織設計41P
- 24蘇州某廠房及配套設施施工平面布置圖匯編
- 25咨詢工程師《方法與實務》案例3:招標與投標
- 26范圍管理不佳引致項目陷入困境
- 27工作索賠按照自由時差還是總時差?
- 28軟土地基雙液注漿工法
- 29防水層倒置施工需注意的幾點
- 30咨詢工程師《宏觀經濟政策與發(fā)展規(guī)劃》自測題(22)
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓