礪志PMP模擬題每周精選2
According to McGregor, a manager who uses Theory X sees workers as--
a. Highly motivated,willing to take responsibility, and reliable
b. Highly untrustworthy, needing to be watched and closely managed at all times
c. Very productive when first given an assignment
d. Unproductive at first, followed by periods of high productivity
Qustions 3:
A Project management information system comprises--
a. Any of the project management software used for schedule development
b. All the requited reports to be prepared on the project, who receives each one, and the method of distribution
c. The policies and procedures to follow as the project is performed
d. The tools and techniques used to gather, integrate, and disseminate the output of the other project management processes
Qustions 5:
The Project plan should be distributed to--
a. All stakeholders in the performing organization
b. All project stakeholders
c. Project team members and the project sponsor
d. Those people defined in the communication management plan
Qustions 2:
Although an output of the various control processes, corrective action is also an input to project plan execution because it--
a. Ensures that project objectives are met
b. Expedites actions to ensure that activities are completed on time
c. Completes the feedback loop needed to ensure effective project management
d. Involves performing a planned reponse for a specific project risk event
Qustions 4:
A change control board is --
a. Recommended for use on all projects, large or small
b. Used as required to approve or reject change requests
c. Managed by the project manager who serves its secretare
d. Composed of key members of the project team
Qustions 6:
Leadership and management are both necessary on projects. One definition of managing is that it involves producing key results expected by stakeholders, whereas leadership involves --
a. Establishing direction, aligning people, and motivating and inspiring others
b. Getting things done through other people
c. Using charismatic power to motivate others to be productive
d. Using all types of power, as appropriate, as motivational tools
- 12015年監(jiān)理工程師《建設(shè)工程三大控制》練習(xí)題(77)
- 22015年安全工程師考試《安全生產(chǎn)管理知識》練習(xí)題(5)
- 3安全工程師輔導(dǎo)資料:如何加強(qiáng)設(shè)備缺陷管理
- 42015年咨詢工程師《項(xiàng)目決策分析與評價》每日一練6.24
- 52015年監(jiān)理工程師考試合同管理歷年考題詳解3
- 6軟件項(xiàng)目管理軟件的開發(fā)計劃
- 7景婺黃(常)高速公路某隧道(實(shí)施)施工組織設(shè)計
- 82015年咨詢工程師《組織與管理》模擬題(3)
- 9坡面砌石防護(hù)施工
- 10陜西造價工程師2013年考試7月19日開始報名
- 112015年監(jiān)理工程師《基本理論和相關(guān)法規(guī)》練習(xí)題(67)
- 122015造價員《安裝工程》基礎(chǔ)知識點(diǎn):金屬管材
- 132015年招標(biāo)師《項(xiàng)目管理與招標(biāo)采購》考前提高試題15
- 142015年咨詢工程師《項(xiàng)目決策分析與評價》每日一練1.24
- 15廣西出臺文明施工導(dǎo)則
- 16錨桿框架護(hù)坡施工方法
- 17監(jiān)理:《建設(shè)工程合同管理》每日一練34
- 182010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案32
- 19安全工程師法規(guī)復(fù)習(xí)要點(diǎn):勞動者的權(quán)利
- 20貴州20多萬戶農(nóng)村危房改造工程進(jìn)入驗(yàn)收階段
- 21監(jiān)理工程師考題精選——質(zhì)量控制(四)
- 22北海路將建下穿進(jìn)港鐵路地道 打通進(jìn)港二線瓶頸
- 23一級建造師工程經(jīng)濟(jì)復(fù)習(xí)要點(diǎn):名義利率
- 24園林鋪地工程施工方案
- 25一級消防工程師備考提高記憶力的七大技巧
- 26工程造價基礎(chǔ)知識招標(biāo)工程量清單的編制:其他項(xiàng)目清單的編制
- 272015年咨詢工程師《工程咨詢概論》每日一練(3.9)
- 282013年西藏二級建造師注冊證書、執(zhí)業(yè)印章遺失補(bǔ)辦申請表
- 29某醫(yī)院外科住院大樓消防工程施工組織設(shè)計59P
- 30安全工程師認(rèn)證首次亮相
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓