1. Communications is best described as:A. an exchange of information.
B. providing written or oral directions.
C. consists of senders and receivers
D. effective listening.
E. All of the above
ANS: E
2. Fixed Price contracts place more risk on the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
3. Life cycle costing is the total cost to the customer for the
acquisition and ownership over its full life. Life cycle costing
categories include the cost
of _____, _____, and _____.
A. R & D, maintainability, operation and support.
B. R & D, production, operation and support.
C. Acquisition, operations, maintenance.
D. Production, operations, maintenance.
E. None of the above
ANS: B
4. Management By Objectives assumes that the team:
A. is receptive to an unstructured environment.
B. does not require close supervision.
C. possesses a self directed philosophy
D. identifies with project objectives.
E. All of the above.
ANS: E
5. Quality may be defined as:
A. conformance to requirements.
B. fitness for use.
C. continuous improvement of products and services
D. appeal to the customer
E. All of the above except B
ANS: E
6. Since risk is associated with most projects, the best course of
action is to:
A. cover all project risks by buying appropriate insurance
B. ignore the risks, since nothing can be done about them and move
forward with the project in an expeditious manner.
C. avoid projects with clear and present risks
D. eliminate all known risks prior to the execution phase of the
project
E. identify various risks and implement actions to mitigate their
potential impact
ANS: E
7. The process of choosing/documenting the best approach to achieve
the project objectives is part of:
A. The scope baseline.
B. Scope authorization
C. Scope definition
D. Scope planning.
E. All of the above.
ANS: D
8. Time management is the allocation of time in a project’s life
cycle through the process of:
A. Planning
B. Estimating.
C. Scheduling.
D. Controlling
E. All of the above.
ANS: E
9. A comprehensive definition of scope management would be:
A. Managing a project in terms of its objective through the concept,
development, implementation, and termination phases of a project.
B. Approval of the scope baseline.
C. Approval of the detailed project charter.
D. Configuration control.
E. Approved detailed planning including budgets, resource allocation,
linear responsibility charts and management sponsorship.
ANS: A
10. Cost Plus Percentage of Cost contracts are more desirable for
the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
- 12015招標(biāo)師考試項(xiàng)目管理考點(diǎn):庫(kù)存管理
- 2高層建筑的高程傳遞方法及精度分析
- 3一級(jí)建造師市政公用工程管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):補(bǔ)償器大集合
- 4國(guó)資委攜84家央企齊聚保定助京津冀協(xié)同發(fā)展
- 5黃河上最寬的中央索面部分矮塔斜拉橋進(jìn)入主梁期
- 6云南省2008年度安全工程師執(zhí)業(yè)資格考試5月10日—6月10日網(wǎng)報(bào)
- 7造價(jià)工程師復(fù)習(xí)資料:在住宅小區(qū)規(guī)劃設(shè)計(jì)中節(jié)約用地的主要措施
- 82015年安全工程師《相關(guān)法律知識(shí)》資料:檢測(cè)檢驗(yàn)機(jī)構(gòu)的資質(zhì)
- 9安全工程師安全生產(chǎn)法復(fù)習(xí)資料——煙花爆竹經(jīng)營(yíng)安全許可證
- 10安全工程師生產(chǎn)法復(fù)習(xí)資料——會(huì)審
- 11北京加強(qiáng)冬季施工綠色管理
- 122015年招標(biāo)師考試:招標(biāo)實(shí)務(wù)問(wèn)答(78)
- 13項(xiàng)目決策分析與評(píng)價(jià)知識(shí)點(diǎn):工藝技術(shù)轉(zhuǎn)讓的形式和方法
- 14名師達(dá)江解答二級(jí)建造師相關(guān)疑問(wèn)——注冊(cè)篇(一)
- 15無(wú)粘接力預(yù)應(yīng)力筋
- 162012年一級(jí)建造師:建筑工程考點(diǎn)總結(jié)(1)
- 17安全文明:機(jī)具、材料管理
- 182015年注冊(cè)咨詢工程師《工程咨詢概論》模擬試題(74)
- 19廣州:農(nóng)民依樣建房可省數(shù)千元
- 202015招標(biāo)師考試科目《項(xiàng)目管理》:招標(biāo)采購(gòu)項(xiàng)目的特點(diǎn)
- 21監(jiān)理工程師應(yīng)組織相關(guān)人員寫(xiě)出質(zhì)量處理報(bào)告,其主要內(nèi)容包括
- 22大跨徑淺埋隧道長(zhǎng)管棚施工工法
- 23工程造價(jià)基礎(chǔ):企業(yè)定額的作用
- 24某工程外墻綜合防水施工方案
- 25安全工程師答疑薈萃:制度與職責(zé)
- 26我國(guó)政府職能轉(zhuǎn)變促使社會(huì)多種中介服務(wù)發(fā)展
- 272015年咨詢工程師《工程咨詢概論》練習(xí)題13
- 28安全工程師答疑精華:反應(yīng)式
- 292015年咨詢工程師《工程咨詢概論》每日一練8.21
- 30安全工程師生產(chǎn)法復(fù)習(xí)資料——安全評(píng)價(jià)機(jī)構(gòu)違反有關(guān)安全評(píng)價(jià)規(guī)則
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓