項目變更控制過程

申請免費試用、咨詢電話:400-8352-114

Introduction (介紹)

Purpose (目的) This document describes the process that is to be used for requesting and managing changes to work products created or maintained by the members of . This process will facilitate communication about requested changes among the stakeholders of , provide a common process for resolving requested changes and reported problems, and reduce the uncertainty around the existence, state, and outcome of a change that has been requested in a work product.

該文檔描述<項目>成員對已創(chuàng)建或維護工件提出變更請求和管理變更時使用的過程。此過程促進了變更請求在<項目>涉眾之間的溝通,以解決變更請求,已報告的問題,以及減少實體,陳述和在一個工件中被提出變更的結(jié)果存在的不確定性提供了共同的過程。

Scope (范圍) Any stakeholder of can submit the following types of issues to the change control system:
  · requests for requirements changes (additions, deletions, modifications, deferrals) in software currently under development
  · reports of problems in current production or beta test systems
  · requests for enhancements in current production systems
  · requests for new development projectsThis change control process applies to baselined work products created or managed by the members of the , including:
  · software that has been released to production or is in beta test
  · requirements specifications for
  · group procedures and processes
  · user and technical documentationThe following work product classes are exempted from this change control process:
  · work products that are still under development, except for requirements changes requested in new projects
  · interim or temporary work products created during the course of a project
  · any work products intended for individual use only

 
任何一個<項目>涉眾都能向變更控制系統(tǒng)提交下列類型的問題:
  ·在軟件處于開發(fā)階段的需求變更請求 (添加, 刪除, 修改, 延期)
&n