PMP認(rèn)證考試練習(xí)題及參考答案(五十四)
申請(qǐng)免費(fèi)試用、咨詢(xún)電話(huà):400-8352-114
1 Which of the following control types has the highest risk to the owner:A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF)
D Cost plus incentive fee (CPIF)
E A and B only
B
2 Which of the following contract types has the highest risk to the contractor:
A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF) 來(lái)源:考試大
D Cost plus incentive fee (CPIF)
E A and B only
A
3 Arbitration is a _____ approach to conflict management in resolving conflict disputes.
A lose-lose
B win-win
C win-lose
D lose-win
E closed door
A
4 Which of the following is not a method of government procurement.
A Assistance
B sealed bidding
C competitive proposals
D acquisition
E small purchases
D
5 The review for the specification completeness is performed during which of the following cycles.
A Award cycles
B requirements cycle
C requisition cycle
D solicitation cycle
E contractual cycle
C
6 In which of the following is the cost of risk hidden by the contractor?
A Firm Fixed Price Contract
B Fixed Price Plus Incentive
C Cost Plus Fixed Price
D Cost Plus Percentage of Cost
E A and B
D
7 The definitive terms of a contract are written during which of the following contract phases?
A Contract Phase
B Post-Award Phase
C Award Phase
D Pre-Award Phase
E Requirement Phase
C
8 The _____ specification delineates specific end use capabilities which can be tested in the acceptance procedure.
A performance
B functional
C technical
D base line http://ks.examda.com
E operational
B
9 Which one of the following is not an acquisition method?
A advertising
B invitation
C negotiation
D purchase
E all are acquisition methods
A
10 Which is not a negotiation tactic?
A Imposing deadlines
B surprises
C person with authority is absent
D reasoning together
E all are negotiations tactics
E
11 A warranty may not be a remedy for products delivered unfit when _____ .
A the PM has knowledge of the product, inspected it without relying on the seller's skill
B the products delivered comply with the plans and specifications of the client
C the plans and specifications produced by the seller match the completed product.
D A and B
E None of the above.
D
12 The Statement of Work (SOW) is developed during the _____ cycle.
A Award
B Solicitations
C requirements
D contractual
E requisitions
C
- 1江西省農(nóng)村危房改造省級(jí)驗(yàn)收工作匯報(bào)會(huì)議召開(kāi)
- 2經(jīng)濟(jì)開(kāi)發(fā)區(qū)園林綠化施工組織設(shè)計(jì)30p
- 3注冊(cè)咨詢(xún)工程師考試《工程咨詢(xún)概論》預(yù)測(cè)試題(4)
- 42015年監(jiān)理工程師《基本理論和相關(guān)法規(guī)》練習(xí)題(15)
- 5杭州招標(biāo)師輔導(dǎo)的課程
- 62012一級(jí)建造師《項(xiàng)目管理》:職業(yè)健康安全事故的分類(lèi)和處理
- 72015年克拉瑪依造價(jià)工程師現(xiàn)場(chǎng)審核地點(diǎn)及時(shí)間
- 8PMP美國(guó)項(xiàng)目管理考試練習(xí)題及答案(七)
- 9建筑病用“繃帶”是遮不住的!
- 10《中外園林史 》教學(xué)大綱
- 112015年安全工程師考試《案例分析》練習(xí)題(18)
- 122015年招標(biāo)師《專(zhuān)業(yè)實(shí)務(wù)》輔導(dǎo):資格預(yù)審概述
- 13造價(jià)工程師復(fù)習(xí)資料:供應(yīng)商參加政府采購(gòu)活動(dòng)應(yīng)當(dāng)具備的條件
- 14錨桿在破壞時(shí)有哪幾種破壞形式?
- 15橋梁混凝土工程雨期施工的技術(shù)要求
- 162015年招標(biāo)師考試《法律法規(guī)與政策》復(fù)習(xí)資料:第四章17
- 172015年安全工程師考試《安全生產(chǎn)法及相關(guān)》練習(xí)題(34)
- 18未來(lái)建筑機(jī)電四大發(fā)展趨勢(shì) BIM應(yīng)用須及時(shí)推進(jìn)
- 19橋梁樁基嵌巖樁底部沉渣的處理
- 202015年安全工程師《相關(guān)法規(guī)》考前小練習(xí)(15)
- 21[重慶]商務(wù)寫(xiě)字樓工程臨時(shí)用水及臨時(shí)用電平面布置圖
- 22招標(biāo)師職業(yè)水平考試:項(xiàng)目管理與招標(biāo)采購(gòu)第二章練習(xí)題18
- 232013年江蘇二級(jí)建造師注銷(xiāo)注冊(cè)申請(qǐng)表
- 242015安全工程師《安全生產(chǎn)事故案例分析》精選例題(3)
- 252012年一級(jí)建造師《建設(shè)工程項(xiàng)目管理》知識(shí)點(diǎn)總結(jié):工程變更權(quán)
- 26深基坑施工事故發(fā)生率高
- 272013年二級(jí)建造師《施工管理》考前復(fù)習(xí)資料(6)
- 28新建貴陽(yáng)至廣州鐵路某隧道(實(shí)施)施工組織設(shè)計(jì)
- 29展望工程造價(jià)未來(lái)
- 30泰安市2015年安全工程師報(bào)名時(shí)間6月7日至6月21日
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓