當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
PMP認證考試練習題及參考答案(五十一)
A Developing system (policies, procedures, responsibilities)
B Obtaining insurance against loss
C performing contingent planning
D developing planning alternatives
E identification of project risks.
ans:E
2 Deflection involves the transfer of risk by:
A Contracting out to another party
B Developing schedule alternative.
C Establishing functions under the project manager to handle risk events.
D Disaster planning and responses.
E None of the above.
ans:A
3 The formalization of management's attitude toward risk is called _____ .
A Decision Theory.
B Utility Theory.
C Decision Tree Analysis.
D Sensitivity Analysis.
E Probability Analysis.
ans:B
4 Risks that cannot be identified or evaluated _____ .
A should be deflected to the contracting officer.
B should be handled via contingency allowances.
C should be ignored, since they cannot be identified.
D should be ignored, since they are not covered in the Risk Assessment.
E C and D
ans:B
5 Range estimating in determining cost risk probabilities requires _____ .
A an amount of financial exposure.
B risks and opportunities ranked in order of bottom line importance
C contingency requirements for expected level of confidence
D probability of cost overrun occurrences
E All of the above.
ans:E
6 Standard deviation of project completion is _____ .
A a relationship of the uncertainty of critical path activities. www.Examda.CoM
B an indicator of project end date target confidence
C a function of critical path, leveling and project costs.
D A and B
E All of the above.
ans:D
7 Which of the following does not contribute to increased Schedule Risk?
A labor shortage
B contractor claims
C lack of access
D sponsor scope changes
E all may increase schedule risk
ans:E
8 Screening of risk events for potential risk is known as _____ .
A problem structuring.
B risk identification
C risk quantification
D risk modeling
E risk mitigation
ans:B
9 The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
ans:B
10 Pure Risk differs from Business Risks because Pure Risk's _____ .
A include chances of both profit or loss associated with the business.
B include chances of loss and no chances for profit associated with the business.
C must incur personal loss with business liability.
D must incur business liability associated with loss of pure profit.
E B and C
ans:B
11 Response Planning is the responsibility of the functional areas and considers
A mitigation.
B deflection.
C contingency planning.
D unforeseen occurrences.
E All of the above.
ans:E
12 Amount at Stake is the _____ .
A function of planned time/real time project costs.
B risk identified in successful project completions.
C (Standard Project Deviation + Expected Costs)/6
D cost of investment loss + least cost to restore status quo.
E inherent risk at conception altered by standard project deviations.
ans:D
- 1某工程消防報警及自動滅火系統(tǒng)施工方案29P
- 2抹灰工程施工過程質量檢查要點
- 3工程管理軟件開發(fā)工具
- 4監(jiān)理工程師考試2015年《工程合同管理》習題(8)
- 5PMP認證考試練習題(一)(中英文)
- 6【學員心聲】監(jiān)理考試高分學員是什么樣的
- 7園林綠化、小品、電氣安裝工程施工
- 82015招標師考試:招標采購專業(yè)實務詳解44
- 9塑料排水板專項施工方案
- 102012一級建造師《公路工程》:工程價款主要結算方式的比較
- 11某文化廣場景觀工程施工組織設計13p
- 122015年咨詢工程師《工程項目組織與管理》每日一練(9.24)
- 13安全工程師安全生產技術復習要點:鍋爐嚴重缺水的處理方法
- 14濕陷性黃土用擠密法
- 15EPS聚苯板外墻外保溫施工工藝
- 16長沙檢驗檢疫局協(xié)助湖南省開辟工程機械出口新領域
- 172015二級建造師《施工管理》掌握關鍵工作和關鍵路線的概念
- 18福建某醫(yī)院病房綜合樓地下室防水施工方案
- 19田桓鐵路將于4月18日正式破土動工
- 20狹長形基坑開挖應符合的規(guī)定
- 21水泥攪拌車養(yǎng)護中要留意哪些問題?
- 22在攪拌車保養(yǎng)中有哪些是只要保養(yǎng)的項目?
- 23某大型企業(yè)施工組織設計編制大綱
- 242015年造價工程師(安裝)知識精講(8)
- 252015一級建造師《市政工程》講義摘要(7)
- 262015年安全工程師《安全生產技術》每日一練(1.31)
- 27造價工程師土建計量復習要點:鋼筋彎曲機、切割機、調直機
- 28攪拌車保養(yǎng)錯誤維護方式
- 29安全工程師法規(guī)復習要點:城鄉(xiāng)規(guī)劃
- 30PMP認證考試練習題及參考答案(二十六)
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓