當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具
PMP認(rèn)證考試練習(xí)題及參考答案(五十一)
A Developing system (policies, procedures, responsibilities)
B Obtaining insurance against loss
C performing contingent planning
D developing planning alternatives
E identification of project risks.
ans:E
2 Deflection involves the transfer of risk by:
A Contracting out to another party
B Developing schedule alternative.
C Establishing functions under the project manager to handle risk events.
D Disaster planning and responses.
E None of the above.
ans:A
3 The formalization of management's attitude toward risk is called _____ .
A Decision Theory.
B Utility Theory.
C Decision Tree Analysis.
D Sensitivity Analysis.
E Probability Analysis.
ans:B
4 Risks that cannot be identified or evaluated _____ .
A should be deflected to the contracting officer.
B should be handled via contingency allowances.
C should be ignored, since they cannot be identified.
D should be ignored, since they are not covered in the Risk Assessment.
E C and D
ans:B
5 Range estimating in determining cost risk probabilities requires _____ .
A an amount of financial exposure.
B risks and opportunities ranked in order of bottom line importance
C contingency requirements for expected level of confidence
D probability of cost overrun occurrences
E All of the above.
ans:E
6 Standard deviation of project completion is _____ .
A a relationship of the uncertainty of critical path activities. www.Examda.CoM
B an indicator of project end date target confidence
C a function of critical path, leveling and project costs.
D A and B
E All of the above.
ans:D
7 Which of the following does not contribute to increased Schedule Risk?
A labor shortage
B contractor claims
C lack of access
D sponsor scope changes
E all may increase schedule risk
ans:E
8 Screening of risk events for potential risk is known as _____ .
A problem structuring.
B risk identification
C risk quantification
D risk modeling
E risk mitigation
ans:B
9 The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
ans:B
10 Pure Risk differs from Business Risks because Pure Risk's _____ .
A include chances of both profit or loss associated with the business.
B include chances of loss and no chances for profit associated with the business.
C must incur personal loss with business liability.
D must incur business liability associated with loss of pure profit.
E B and C
ans:B
11 Response Planning is the responsibility of the functional areas and considers
A mitigation.
B deflection.
C contingency planning.
D unforeseen occurrences.
E All of the above.
ans:E
12 Amount at Stake is the _____ .
A function of planned time/real time project costs.
B risk identified in successful project completions.
C (Standard Project Deviation + Expected Costs)/6
D cost of investment loss + least cost to restore status quo.
E inherent risk at conception altered by standard project deviations.
ans:D
- 1某工程消防報(bào)警及自動(dòng)滅火系統(tǒng)施工方案29P
- 2抹灰工程施工過程質(zhì)量檢查要點(diǎn)
- 3工程管理軟件開發(fā)工具
- 4監(jiān)理工程師考試2015年《工程合同管理》習(xí)題(8)
- 5PMP認(rèn)證考試練習(xí)題(一)(中英文)
- 6【學(xué)員心聲】監(jiān)理考試高分學(xué)員是什么樣的
- 7園林綠化、小品、電氣安裝工程施工
- 82015招標(biāo)師考試:招標(biāo)采購專業(yè)實(shí)務(wù)詳解44
- 9塑料排水板專項(xiàng)施工方案
- 102012一級(jí)建造師《公路工程》:工程價(jià)款主要結(jié)算方式的比較
- 11某文化廣場景觀工程施工組織設(shè)計(jì)13p
- 122015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練(9.24)
- 13安全工程師安全生產(chǎn)技術(shù)復(fù)習(xí)要點(diǎn):鍋爐嚴(yán)重缺水的處理方法
- 14濕陷性黃土用擠密法
- 15EPS聚苯板外墻外保溫施工工藝
- 16長沙檢驗(yàn)檢疫局協(xié)助湖南省開辟工程機(jī)械出口新領(lǐng)域
- 172015二級(jí)建造師《施工管理》掌握關(guān)鍵工作和關(guān)鍵路線的概念
- 18福建某醫(yī)院病房綜合樓地下室防水施工方案
- 19田桓鐵路將于4月18日正式破土動(dòng)工
- 20狹長形基坑開挖應(yīng)符合的規(guī)定
- 21水泥攪拌車養(yǎng)護(hù)中要留意哪些問題?
- 22在攪拌車保養(yǎng)中有哪些是只要保養(yǎng)的項(xiàng)目?
- 23某大型企業(yè)施工組織設(shè)計(jì)編制大綱
- 242015年造價(jià)工程師(安裝)知識(shí)精講(8)
- 252015一級(jí)建造師《市政工程》講義摘要(7)
- 262015年安全工程師《安全生產(chǎn)技術(shù)》每日一練(1.31)
- 27造價(jià)工程師土建計(jì)量復(fù)習(xí)要點(diǎn):鋼筋彎曲機(jī)、切割機(jī)、調(diào)直機(jī)
- 28攪拌車保養(yǎng)錯(cuò)誤維護(hù)方式
- 29安全工程師法規(guī)復(fù)習(xí)要點(diǎn):城鄉(xiāng)規(guī)劃
- 30PMP認(rèn)證考試練習(xí)題及參考答案(二十六)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓