2010年pmp美國項目管理考試項目成本管理練習(xí)題及答案4
1. Looking across the majority of industries, during which phase in a project life cycle are most of the project expenses incurred?
A. Concept phase
B. Development or design phase
C. Execution phase
D. Termination phase
對于大多數(shù)的產(chǎn)業(yè), 項目費用大多發(fā)生在項目生命周期中的哪一階段?
A. 構(gòu)思階段
B. 開發(fā)或設(shè)計階段
C. 執(zhí)行階段
D. 結(jié)束階段
2. Using the table below, the schedule performance index (SPI) for WBS Element P is:
A. 1.10
B. 0.90
C. 0.956
D. 1.15
WBS Element BCWS BCWP ACWP
P $1,000 $1,100 $1,150
Q $2,000 $1,800 $2,100
R $1,000 $1,200 $1,050
S $2,000 $1,900 $1,800
用下表數(shù)據(jù)計算, 工作分解結(jié)構(gòu)WBS要素P的進(jìn)度績效指數(shù)(SPI)是:
A. 1.10
B. 0.90
C. 0.956
D. 1.15
工作分解結(jié)構(gòu)WBS 要素 計劃執(zhí)行預(yù)算成本BCWS 已執(zhí)行工作預(yù)算成本BCWP 已執(zhí)行工作實際成本ACWP
P $1,000 $1,100 $1,150
Q $2,000 $1,800 $2,100
R $1,000 $1,200 $1,050
S $2,000 $1,900 $1,800
3. You have estimated and scheduled your project based on the team members you have been assigned and developed the BCWS baseline. However, you have now been assigned new team members who are more experienced and higher salaried than those on which you based your initial estimate. The most probable impact on project performance would be:
A. Negative CV, negative SV
B. Negative CV, positive SV
C. Positive CV, negative SV
D. Positive CV, positive SV
你對項目進(jìn)行了估算和進(jìn)度安排,根據(jù)團(tuán)隊成員情況, 分配了任務(wù)并且制定了計劃執(zhí)行
預(yù)算成本的基準(zhǔn). 然而,分配了新的項目團(tuán)隊成員, 他們比初始估算的成員更有經(jīng)驗,薪水
更高.這對項目績效最可能的影響會是:
A. 負(fù)的成本偏差CV, 負(fù)的進(jìn)度偏差SV
B. 負(fù)的成本偏差CV, 正的進(jìn)度偏差SV
C. 正的成本偏差CV, 負(fù)的進(jìn)度偏差SV
D. 正的成本偏差CV, 正的進(jìn)度偏差SV
4. The most precise and accurate technique for determining project costs is the technique.
A. Bottom-up
B. Analogy
C. Budget
D. Modified standards
決定項目成本的最精確的和最正確的技術(shù)是什么技術(shù)
A. 由下而上
B. 類比
C. 預(yù)算
D. 修正標(biāo)準(zhǔn)
5. The four types of cost data that are normally accumulated and reported as part of a cost control system are:
A. Labor, material, other direct charges, management reserve
B. Labor, material, management reserve, overhead
C. Management reserve, labor, other direct charges, overhead
D. Labor, material, other direct charges, overhead
作為成本控制系統(tǒng)的一部份,要收集并且報告的四類成本數(shù)據(jù)是:
A. 人工,原材料,其它直接費用, 管理儲備
B. 人工原材料,管理儲備,管理費用
C. 管理儲備人工, 其它直接費用, 管理費用
D. 人工原材料, 其它直接費用,管理費用
6. The techniques commonly used to determine the profitability of a project include all of the following, except:
A. Net present value (NPV) B. Internal rate of return (IRR)
C. Payback period
D. Risk assessment model (RAM)
通常用來計算決定項目的獲利力的技術(shù)包括所有的下列項,除了:
A. 凈現(xiàn)值 (NPV)
B. 內(nèi)部的回報率 (IRR)
C. 投資回收期
D. 風(fēng)險評估模型(RAM)
7. Which of the following is not considered a direct cost for producing a widget?
A. The cost of the materials used to produce a widget
B. The labor costs of the workers who actually produced the widget
C. The rent for the building in which the widget was manufactured
D. The equipment used to produce the widget
下列哪一項不會被考慮作為生產(chǎn)小器具的直接成本?
A. 用于生產(chǎn)小器具的原材料的成本
B. 實際生產(chǎn)小器具的人工成本
C. 生產(chǎn)制造小器具的廠房場地的租金
D. 生產(chǎn)小器具的設(shè)備
8. Which of the following would not necessarily increase the accuracy of estimating the project cost?
A. Pricing out the work at lower levels in the work breakdown structure
B. Using historical data
C. Talking to people who have worked on similar project
D. Spending additional time on the estimate
下列的哪一項不會必然地增加估算項目成本的準(zhǔn)確性?
A. 在工作分解結(jié)構(gòu)中, 在較低的水平訂定工作價格
B. 使用歷史數(shù)據(jù)
C. 與有類似項目工作經(jīng)驗的人進(jìn)行交流
D. 花額外的時間進(jìn)行估算
9. What tool must project managers rely upon to accurately identify the costs associated with a project?
A. A bill of materials
B. A Gantt chart
C. An arrow diagram network
D. A work breakdown structure
項目經(jīng)理必須依賴什么工具,以便準(zhǔn)確識別與項目相關(guān)聯(lián)的成本?
A. 材料單
B. 甘特圖
C. 箭線網(wǎng)絡(luò)圖
D. 工作分解結(jié)構(gòu)
10. Using the table below, WBS Element Q is budget by percent.
A. Over, 16.66
B. Under, 16.66
C. Over, 10.0
D. Under, 10.0
WBS Element BCWS BCWP ACWP
P $1.000 $1,100 $1,150
Q $2,000 $1,800 $2,100
R $1,000 $1,200 $1,050
S $2,000 $1,900 $1,800
利用下表數(shù)據(jù), 工作分解結(jié)構(gòu)WBS 要素Q是預(yù)算多少百分比
A. 超過,16.66
B. 低于,16.66
C. 超過,10.0
D. 低于,10.0
工作分解結(jié)構(gòu)要素 計劃執(zhí)行預(yù)算成本BCWS 已執(zhí)行工作預(yù)算成本BCWP 已執(zhí)行工作實際成本ACWP
P $1.000 $1,100 $1,150
Q $2,000 $1,800 $2,100
R $1,000 $1,200 $1,050
S $2,000 $1,900 $1,800
11. Using the table below, the labor rate cost variance is:
A. $68,329.00
B. $386.00
C. ($0.22)
D. $18.36
Direct Labor Direct Material
Planned price/unit $10.50 $14.77
Actual units/hour 6374 hrs. 5433 units
Actual cost $68,329 $83.994
Actual price/unit $10.72 $15.46
利用下表數(shù)據(jù)計算,人工費用成本偏差是:
A. $68,329.00
B. $386.00
C. ($0.22)
D. $18.36
直接人工 直接原材料
單位計劃價格 $10.50 $14.77
每小時實際單位 6374 hrs. 5433 units
實際成本 $68,329 $83.994
單位實際價格 $10.72 $15.46
12. Using the table below, which WBS element is behind schedule but under budget?
A. Element P
B. Element Q
C. Element R
D. Element S
WBS Element BCWS BCWP ACWP
P $1.000 $1.100 $1.150
Q $2.000 $1.800 $2.100
R $1.000 $1.200 $1.050
S $2.000 $1.900 $1.800
利用下表數(shù)據(jù)計算, 工作分解結(jié)構(gòu)WBS的哪一要素是落后進(jìn)度但低于預(yù)算?
A. 要素 P
B. 要素 Q
C. 要素 R
D. 要素 S
工作分解結(jié)構(gòu)WBS 要素 計劃執(zhí)行預(yù)算成本BCWS 已執(zhí)行工作預(yù)算成本BCWP 已執(zhí)行工作實際成本ACWP
P $1.000 $1.100 $1.150
Q $2.000 $1.800 $2.100
R $1.000 $1.200 $1.050
S $2.000 $1.900 $1.800
13. Company expenses such as auditing costs, supervision, office supplies, building rent, and maintenance are elements of the:
A. Capital budgeting process
B. Overhead rates
C. Contracts and administration costing system
D. Fringe benefits package
公司費用,如審計成本管理監(jiān)督辦公用品費用,建筑場地租用費維修費是屬于:
A. 資本預(yù)算編制過程
B. 管理費用
C. 合同和管理費用系統(tǒng)
D. 福利開支
14. Life cycle costing to the customer for the acquisition of a system includes the following categories:
A. R&D, maintainability, operation, and support
B. Acquisition, operations, and maintenance
C. R&D, production, operation, and support
D. Production, operations, and maintenance
項目生命周期中,客戶外購系統(tǒng)開支包括下列種類:
A. 研究開發(fā)R&D 維修操作和輔助服務(wù)
B. 收購操作和維修
C. R&D 生產(chǎn)制造操作和輔助服務(wù)
D. 生產(chǎn)制造操作和維修
15. The three most common techniques for developing project cost estimates are:
A. Budgetary, team-based and parametric
B. Analogous, top-down and bottom-up
C. Analogous, parametric and direct
D. Analogous, parametric, and bottom-up
制定項目成本概算的三個最通常的技術(shù)是:
A. 預(yù)算式, 團(tuán)隊式的和參數(shù)式
B. 類比式,由上而下式和由下而上式
C. 類比式,參數(shù)式和直接式
D. 類比式,參數(shù)式和由下而上式
16. The future value of an annual income flow of $1,000 for 2 years at 10% is:
A. $2.200
B. $2.280
C. $2.300
D. $2.310
利率10%, 2 年期每年收入流$1,000, 其未來價值是:
A. $2.200
B. $2.280
C. $2.300
D. $2.310
17. Methods and techniques used to examine cost and technical data are called feasibility studies. The economic aspects of a feasibility study include interest rates, present worth factors, operation costs, depreciation, and .
A. Capitalization costs
B. Technical skill requirements
C. Technology forecasting
D. Strategic marketing intelligence
用于審核成本和有關(guān)數(shù)據(jù)的方法和技術(shù)被稱為可行性研究可行性研究考慮的經(jīng)濟(jì)方面包括利率現(xiàn)值因素操作成本,折舊,和
A. 資本化成本
B. 技術(shù)性技能要求
C. 技術(shù)預(yù)測
D. 戰(zhàn)略行銷情報
18. Upon completion of 75% of the project, the original schedule and cost estimate that were submitted at the inception of the project are referred to as the:
A. Baseline
B. Budgeted costs
C. Estimates upon completion costs
D. Scheduled costs
以完成項目75%為基礎(chǔ)在項目啟動時遞交的最初的進(jìn)度和成本估算被稱為:
A. 基準(zhǔn)計劃書
B. 預(yù)算成本
C. 完工成本估算
D. 安排計劃成本
19. A project manager is trying to better manage the cost of the projects taking place within the Information Technology business unit. Which of the following generic life cycle phases would allow the project manager to have the most impact on managing cost?
A. Closeout
B. Execution
C. Installation
D. Concept and Design
對于發(fā)生在信息技術(shù)事業(yè)部的項目成本,某項目經(jīng)理正試圖較好地加以管理
下列哪一生命周期階段使項目經(jīng)理對于管理成本有最大的影響?
A. 收尾
B. 實施
C. 安裝
D. 構(gòu)思和設(shè)計
20. The methods and techniques for determining the economic costs, the environmental 藏impact, the economic returns, and the probability for success are called:
A. Feasibility studies
B. Bills of materials
C. PERT charts
D. Management reserve
參考答案:
1、CABBD DCDDA11、CDBBD DAADA
相關(guān)試題:
2010年pmp美國項目管理考試項目成本管理練習(xí)題及答案1
2010年pmp美國項目管理考試項目成本管理練習(xí)題及答案2
2010年pmp美國項目管理考試項目成本管理練習(xí)題及答案3
- 1【經(jīng)驗之談】天道酬勤 通過二建離不開勤奮
- 2一級建造師《建設(shè)工程經(jīng)濟(jì)》重點解析(17)
- 3全國監(jiān)理工程師臨考密押試卷《建設(shè)工程合同管理》(二)
- 4攪拌車的車身抖動有隱患
- 52015年上海造價工程師考試報名時間通知
- 6一級建造師工程經(jīng)濟(jì)復(fù)習(xí)要點:施工定額和企業(yè)定額的編制
- 7某大廈給排水系統(tǒng)的設(shè)計實例 4P
- 82015年一級建造師考試《法規(guī)及相關(guān)知識》沖刺習(xí)題(15)
- 9斜切式洞門隧道實施性施工組織設(shè)計109頁(明挖法 臺階法 2013年)
- 10安全工程師答疑精華:建筑機(jī)械
- 112015年安全工程師考試安全生產(chǎn)管理知識練習(xí)題(10)
- 12咨詢方法與實務(wù)考點:市場預(yù)測的主要方法
- 13一級建造師管理與實務(wù)復(fù)習(xí)要點:鋼絞線檢驗
- 142015年雙鴨山造價工程師報名時間
- 15混凝土柱碳纖維加固施工工藝
- 162015年咨詢工程師《宏觀經(jīng)濟(jì)政策與發(fā)展規(guī)劃》每日一練9.28
- 17城市園林綠地規(guī)劃學(xué)課件
- 182015年安全工程師考試《管理知識》經(jīng)典練習(xí)(10)
- 19石質(zhì)路塹施工
- 20中國首座深水天然氣處理終端施工完成總進(jìn)度74%
- 21延長石油頁巖氣項目獲國家四億元資金支持
- 222015年安全工程師《安全生產(chǎn)法及相關(guān)》輔導(dǎo)資料(7)
- 23某綜合樓基礎(chǔ)施工階段平面布置圖
- 24某住宅小區(qū)環(huán)境配套工程施工方案
- 25北京某住宅地下防水施工方案(剛?cè)峤Y(jié)合)
- 262015造價員《土建工程》墻與框架結(jié)構(gòu):圈梁
- 272015年招標(biāo)師采購專業(yè)實務(wù)全真模擬題6
- 282015年內(nèi)蒙古造價工程師考試報名時間為6月7日-12日
- 292015年安全工程師考試《案例分析》練習(xí)題(33)
- 30污水處理廠改造施工組織設(shè)計 39P
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓