QUEST The project charter is developed by:
A senior management
B the customer
C the project manager
D both A and C
E None of the above.
參考答案:D
QUEST A program is characterized as:
A a grouping or related tasks lasting one year or less.
B a unique undertaking having a definite time period.
C a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.
D a project with a cost over $1 million.
E None of the above.
參考答案:C
QUEST Creation of project objectives:
A allows for data collection and analysis and progress reporting against which standards of performance can be measured.
B is accomplished by selection of measurable variables against which performance can be judged.
C is required before funding of the project by the project sponsor.
D all of the above.
E A and B only
參考答案:E
QUEST A project is defined as:
A a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.
B a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.
C an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.
D a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.
E All of the above.
參考答案:A
QUEST The use of the project reports:
A are not necessary on small projects
B provides a means whereby various levels of authority can judge project performance
C provides insight into project areas and the effectiveness of the control systems
D All of the above
E B and C
參考答案:E
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案十二
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
- 1崇左某辦公樓屋面及衛(wèi)生間防水施工工藝
- 2我的考試之心得 09年監(jiān)理考試通過(guò)后記
- 3項(xiàng)目信息管理系統(tǒng)應(yīng)滿(mǎn)足下列要求主要內(nèi)容
- 4豎井施工方法
- 5新型梁模合一型移動(dòng)模架施工工法(部級(jí)工法獎(jiǎng))
- 6安全工程師《安全生產(chǎn)管理》第三講講義精選(8)
- 7二級(jí)建造師考試復(fù)習(xí)總結(jié):施工組織設(shè)計(jì)編制的程序
- 8杭長(zhǎng)客專(zhuān)東孝聯(lián)絡(luò)線(xiàn)特大橋金東村連續(xù)梁混凝土澆筑完成
- 9認(rèn)證機(jī)構(gòu)對(duì)獲準(zhǔn)認(rèn)證的供方質(zhì)量管理體系實(shí)施監(jiān)督管理
- 10湖南:張花高速公路今年9月底通車(chē) 全長(zhǎng)146.848公里
- 112015年安全工程師《安全生產(chǎn)法及相關(guān)法律知識(shí)》每日一練(4.8)
- 12安全工程師考試《法律法規(guī)》習(xí)題班第八講講義(9)
- 13石灰處治膨脹土路基填料的應(yīng)用
- 142008年安全工程師考試《安全生產(chǎn)法及相關(guān)法律知識(shí)》習(xí)題十七
- 15工程結(jié)算的意義
- 16二級(jí)建造師法規(guī)知識(shí)點(diǎn):標(biāo)的物毀損滅失風(fēng)險(xiǎn)
- 17晉豫魯鐵路湯陰段全線(xiàn)通電
- 182015年安全工程師相關(guān)法律知識(shí)練習(xí)(11)
- 192015年一級(jí)建造師《建設(shè)工程項(xiàng)目管理》知識(shí)點(diǎn)歸納(4)
- 202013年二級(jí)建造師《法規(guī)》重點(diǎn):不需要申請(qǐng)施工許可證的工程類(lèi)型
- 21安全工程師考點(diǎn):民用爆炸物品安全管理?xiàng)l例適用范圍
- 22[中建]住宅樓地下防水工程施工方案(SBS防水卷材)
- 23在結(jié)構(gòu)工程施工中對(duì)已安裝的模板、架立的鋼筋等應(yīng)進(jìn)行什么檢驗(yàn)
- 24下列關(guān)于最低評(píng)標(biāo)價(jià)法的說(shuō)法中,正確的是
- 25攪拌車(chē)日常如何正確的使用千斤頂
- 26安全工程師考試《法律法規(guī)》習(xí)題班講義精選(36)
- 272015年監(jiān)理工程師考試合同管理練習(xí)題(32)
- 28劉永強(qiáng)老師講得很透徹 準(zhǔn)媽媽順利通過(guò)2013二建水利增項(xiàng)
- 29鋼筋混凝土預(yù)制沉井施工
- 302015咨詢(xún)工程師《現(xiàn)代咨詢(xún)方法與實(shí)務(wù)》備考試題(2)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓