監(jiān)理公司管理系統(tǒng) | 工程企業(yè)管理系統(tǒng) | OA系統(tǒng) | ERP系統(tǒng) | 造價咨詢管理系統(tǒng) | 工程設計管理系統(tǒng) | 甲方項目管理系統(tǒng) | 簽約案例 | 客戶案例 | 在線試用
X 關閉
軟件項目管理工具

當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具

2010年PMP美國項目管理考試習題及答案二十二

申請免費試用、咨詢電話:400-8352-114

QUEST A completion of a local government study resides on your critical path.  This would most likely be referred to as: 
A Soft logic 
B Hard logic 
C An external dependency 
D A mandatory dependency 
E A lost cause 
參考答案:C

QUEST Which of the following can affect network durations? 
A Skills of the resource pool 
B Calendar dates 
C Constraints 
D All of the above 
E A and B only 
參考答案:E

QUEST Sources for data on activity durations and resource requirements can be gathered from which of the following: 
A Past project records (historical data) 
B Commercial techniques (standard practices, rules of thumb) 
C Past project team members knowledge (experience, oldtimers) 
D All of the above 
E A and C only 
參考答案:D

QUEST The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency. 
A Discretionary 
B Mandatory 
C External 
D Soft logic 
E Subcontracted 
參考答案:B

QUEST "Hard logic" in the preparation of a network refers to: 
A Discretionay dependencies 
B External depenencies 
C Mandatory dependencies 
D All of the above 
E A abd B only 
參考答案:C

相關試題:

2010年PMP美國項目管理考試習題及答案二十一

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:55    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件