QUEST In the PDM, common constraints include: 
A Start-to-start 
B Finish-to-start 
C Finish-to-finish 
D B and C only 
E A, B, and C. 
參考答案:E

QUEST Activities with zero time duration are referred to as: 
A Critical path activites. 
B Noncritical path activities. 
C Slack time activities. 
D Dummies 
E None of above. 
參考答案:D

QUEST In the arrow diagramming method (ADM), _____ do not consume time or resources. 
A Events. 
B Activities 
C Slack elements. 
D B and C only. 
E All of the above. 
參考答案:A

QUEST On a precedence diagram, the arrow between two boxes is called: 
A An activity. 
B A constraint. 
C An event. 
D The critical path. 
E None of above. 
參考答案:B

QUEST A project element which lies between two events is called: 
A An activity. 
B A critical path method. 
C A slack milestone. 
D A timing slot. 
E A calendar completion point. 
參考答案:A

相關試題:

2010年PMP美國項目管理考試習題及答案三十五

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件