PMP項目管理:項目溝通管理練習題3
1.An informal communication network on a project or within an organization is created through:
A.Free upward flow
B.Free horizontal flow
C.Unrestricted communication flow
D.The project manager’s ability to make use of his/her unofficial relationships with stakeholders 在項目或一個組織內(nèi)部建立一個非正式的溝通網(wǎng)絡是通過:
A.向上自由流
B.水平自由流
C.不受限制的交流
D.項目經(jīng)理利用其與項目利害相關者的非正式的關系的能力
2.For every project situation, several methods usually exist for effective communication to take place.Which of the following is least likely to be used for explaining to the team the project planning guidelines?
A.Project office memo
B.Project office directive
C.Project team meeting
D.Formal report
對于每個項目情形通常有幾種有效的溝通方法可以進行在向團隊解釋項目計劃編制指導方針時,下列哪一項最不可能被運用?
A.項目辦公室備忘錄
B.項目辦公室指示
C.項目團隊會議
D.正式的報告
3.A project manager, who is trying to communicate accurately to the team, should understand and use:
A.A language appropriate to the needs of the stakeholders
B.The language of the project manager
C.Non-verbal methods
D.Written memos
A 項目經(jīng)理正在嘗試與團隊進行準確的溝通,應該了解并使用:
A.符合項目利害相關者需要的適當?shù)恼Z言
B.項目經(jīng)理的語言
C.非言語方式
D.書面?zhèn)渫?
4.The project proceeded successfully until the customer asked for additional work not included in the contract.At that point the project team began to make changes to the specifications, delivery date, and schedule.What communication device should the project manager have demanded before any work was modified?
A.Meeting with the sponsor
B.Formal, written correspondence with the customer
C.Memo from the customer
D.Memo to the customer
正當項目順利進行時,客戶突然要求做沒有包括在合同中的額外的工作這時項目團隊開始對規(guī)格, 交貨日期和進度來作些變更在調(diào)整進行任何工作之前, 項目經(jīng)理應該需要獲得什么溝通工具?
A.與業(yè)主的會議
B.與客戶的正式的書面溝通
C.來自客戶的備忘錄
D.發(fā)給客戶的備忘錄
5.Project managers who are available to answer questions, provide guidance when needed, and generally do not interfere with day-to-day activities have a(n) ____________ managerial and communicating style.
A.Autocratic
B.Conciliatory
C.Facilitative
D.Judicial
項目經(jīng)理能隨時回答問題,若需要時提供指導,并且通常不干預日常的活動,其是_______ 管理的和溝通風格
A.專制式
B.安撫式
C.促進式
D.法制式
6.If a project manager emphasizes those areas where he is in agreement with the functional manager and down plays other conflicts, the project manager can be said to be using which of the following to address the conflict:
A.Withdrawal
B.Smoothing
C.Compromising
D.Confrontation
如果一個項目經(jīng)理強調(diào)與職能經(jīng)理一致的方面,淡化其它沖突,則說明項目經(jīng)理運用了下列哪一方式來對待處理矛盾沖突:
A.回避
B.協(xié)商處理
C.妥協(xié)處理
D.正面對抗
7.The degree to which project team members can successfully communicate with the project manager depends primarily upon:
A.How effectively the project manager establishes relationships with the team
B.The project manager ’s level in the organizational hierarchy
C.The size and nature of the project
D.The project manager ’s salary and age
項目團隊成員能與項目經(jīng)理成功溝通的程度主要地取決于:
A.項目經(jīng)理如何有效地與團隊建立關系
B.項目經(jīng)理在組織層級中的地位
C.項目的規(guī)模和性質(zhì)
D.項目經(jīng)理的薪水和年齡
8.Project communication management is best described as conducting or supervising _________.
A.The way we listen
B.The way we speak
C.The way we feel
D.The exchange of project information
項目溝通管理可以最適當?shù)孛枋鰹橐龑Щ虮O(jiān)督 _________.
A.我們傾聽的方式
B.我們說的方式
C.我們感覺的方式
D.項目信息的交換
9.If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume that:
A.The message was understood
B.The message was not understood
C.The message may or not have been understood
D.The information was not appropriate
如果一個項目經(jīng)理向下屬傳達了一個口述的信息, 并且下屬沒有說話就離開走了項目經(jīng)理應該假定:
A.信息被理解了
B.信息沒被理解
C.信息可能被理解
D.信息不適當
10.The project manager who allows and supports group discussions and decision-making is called a (n) _______ manager.
A.Autocratic
B.Ethical
C.Conciliatory
D.Delegating
允許并且?guī)椭С謭F隊進行討論和決策的項目經(jīng)理人被稱為_______經(jīng)理
A.專制式
B.倫理式
C.安撫式
D.授權式
- 12015年注冊咨詢工程師《工程咨詢概論》練習題(109)
- 2編制投標書常見的115個錯誤(六)
- 3工程項目組織與管理知識點:社會技術支持的管理
- 4造價工程師土建計量復習要點:涂料
- 52015年監(jiān)理工程師《工程質(zhì)量與進度控制》(1)
- 6礪志PMP模擬題本周精選12
- 7【經(jīng)驗之談】名師伴我行 我一定能行
- 82015年咨詢工程師《工程咨詢概論》每日一練12 .19
- 92015年注冊安全工程師考試考前沖刺試題精選(15)
- 102015安全工程師相關法律知識:安全生產(chǎn)標準制定修訂程序
- 11某引橋高墩柱施工
- 12美國項目管理PMP認證模擬考試試題精選4
- 13瀘州市城鄉(xiāng)風貌塑造進展順利
- 142015年造價員基礎知識:招標文件的組成與內(nèi)容
- 152015年招標師:招標采購實務模擬試題21
- 16某區(qū)室外排水管道施工方案8P
- 17湖北省某隧道工程施工組織設計
- 18混凝土攪拌車保養(yǎng)要領溫馨提示
- 19揚州市2015年造價工程師考試報名時間為6月12至27日
- 20分享:2015年備考造價員考試心得
- 21湖北:2014年建設農(nóng)村公路14233公里
- 222015年一級建造師考試輔導:項目管理規(guī)范(十八)
- 23水下混凝土灌注施工卡管防治措施
- 24二建施工管理重難點:職業(yè)健康安全與環(huán)境管理的特點和要求
- 25梅州市2015年安全工程師考試報名時間為4月13日至5月14日
- 26江西省2015年安全工程師考試報名時間為4月6日-14日
- 27園林工程施工與組織管理課件
- 28GFZ聚乙烯丙綸復合防水體系施工工藝
- 29安全工程師考試《安全生產(chǎn)技術》重點題目(二十三)
- 302015年安全工程師考試安全生產(chǎn)管理知識練習題(11)
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓